Washington § 80.60.040 - Safety, power quality, and interconnection requirements — Customer-generator's expense — Commission may adopt additional requirements.

Full text of Washington Revised Code of Washington § 80.60.040 — Safety, power quality, and interconnection requirements — Customer-generator's expense — Commission may adopt additional requirements., with citation guidance and answers to common questions.

§ 80.60.040. Safety, power quality, and interconnection requirements — Customer-generator's expense — Commission may adopt additional requirements.

(1) A net metering system used by a customer-generator shall include, at the customer-generator's own expense, all equipment necessary to meet applicable safety, power quality, and interconnection requirements established by the national electrical code, national electrical safety code, the institute of electrical and electronics engineers, and underwriters laboratories.
(2) The commission, in the case of an electrical company, or the appropriate governing body, in the case of other electric utilities, after appropriate notice and opportunity for comment, may adopt by regulation additional safety, power quality, and interconnection requirements for customer-generators, including limitations on the number of customer-generators and total capacity of net metering systems that may be interconnected to any distribution feeder line, circuit, or network that the commission or governing body determines are necessary to protect public safety and system reliability.
(3) An electric utility may not require a customer-generator whose net metering system meets the standards in subsections (1) and (2) of this section to comply with additional safety or performance standards, perform or pay for additional tests, or purchase additional liability insurance. However, an electric utility shall not be liable directly or indirectly for permitting or continuing to allow an attachment of a net metering system, or for the acts or omissions of the customer-generator that cause loss or injury, including death, to any third party.
(4) Except when required under the federal public utility regulatory policies act, an electric utility may not establish compensation arrangements or interconnection requirements, other than those permitted in this chapter, for a customer-generator that would have the effect of prohibiting or restricting the ability of a customer-generator to generate or store electricity for consumption on its premises.
[ 2019 c 235 s 4; 2006 c 201 s 4; 2000 c 158 s 3; 1998 c 318 s 5.]

Source: official Washington text · Last verified 2026-08-27

Frequently Asked Questions About Washington § 80.60.040

What does Revised Code of Washington § 80.60.040 cover?

Section 80.60.040 ("Safety, power quality, and interconnection requirements — Customer-generator's expense — Commission may adopt additional requirements.") is part of the Revised Code of Washington, the codified statutory law of Washington. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Washington § 80.60.040?

A common citation format is "Revised Code of Washington § 80.60.040" (Washington). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Washington law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Washington official source linked on this page or consult a licensed Washington attorney.

How does Washington § 80.60.040 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Washington can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Washington.