Washington § 78.56.090 - Initial waste discharge permits for tailings facilities — Siting criteria — Primary screening process — Technical site investigation — Site selection report.

Full text of Washington Revised Code of Washington § 78.56.090 — Initial waste discharge permits for tailings facilities — Siting criteria — Primary screening process — Technical site investigation — Site selection report., with citation guidance and answers to common questions.

§ 78.56.090. Initial waste discharge permits for tailings facilities — Siting criteria — Primary screening process — Technical site investigation — Site selection report.

(1) In the processing of an application for an initial waste discharge permit for a tailings facility pursuant to the requirements of chapter 90.48 RCW, the department of ecology shall consider site-specific criteria in determining a preferred location of tailings facilities of metals mining and milling operations and incorporate the requirements of all known available and reasonable methods in order to maintain the highest possible standards to insure the purity of all waters of the state in accordance with the public policy identified by RCW 90.48.010.
In implementing the siting criteria, the department shall take into account the objectives of the proponent's application relating to mining and milling operations. These objectives shall consist of, but not be limited to (a) operational feasibility, (b) compatibility with optimum tailings placement methods, (c) adequate volume capacity, (d) availability of construction materials, and (e) an optimized embankment volume.
(2) To meet the mandate of subsection (1) of this section, siting of tailings facilities shall be accomplished through a two-stage process that consists of a primary alternatives screening phase, and a secondary technical site investigation phase.
(3) The primary screening phase will consist of, but not be limited to, siting criteria based on considerations as to location as follows:
(a) Proximity to the one hundred year floodplain, as indicated in the most recent federal emergency management agency maps;
(b) Proximity to surface and ground water;
(c) Topographic setting;
(d) Identifiable adverse geologic conditions, such as landslides and active faults; and
(e) Visibility impacts of the public generally and residents more particularly.
(4) The department of ecology, through the primary screening process, shall reduce the available tailings facility sites to one or more feasible locations whereupon a technical site investigation phase shall be conducted by the department for the purpose of verifying the adequacy of the remaining potential sites. The technical site investigations phase shall consist of, but not be limited to, the following:
(a) Soil characteristics;
(b) Hydrologic characteristics;
(c) A local and structural geology evaluation, including seismic conditions and related geotechnical investigations;
(d) A surface water control analysis; and
(e) A slope stability analysis.
(5) Upon completion of the two phase evaluation process set forth in this section, the department of ecology shall issue a site selection report on the preferred location. This report shall address the above criteria as well as analyze the feasibility of reclamation and stabilization of the tailings facility. The siting report may recommend mitigation or engineering factors to address siting concerns. The report shall be developed in conjunction with the preparation of and contained in an environmental impact statement prepared pursuant to chapter 43.21C RCW. The report may be utilized by the department of ecology for the purpose of providing information related to the suitability of the site and for ruling on an application for a waste discharge permit.
(6) The department of ecology may, at its discretion, require the applicant to provide the information required in either phase one or phase two as described in subsections (3) and (4) of this section.
[ 1994 c 232 s 9.]

Source: official Washington text · Last verified 2026-08-27

Frequently Asked Questions About Washington § 78.56.090

What does Revised Code of Washington § 78.56.090 cover?

Section 78.56.090 ("Initial waste discharge permits for tailings facilities — Siting criteria — Primary screening process — Technical site investigation — Site selection report.") is part of the Revised Code of Washington, the codified statutory law of Washington. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Washington § 78.56.090?

A common citation format is "Revised Code of Washington § 78.56.090" (Washington). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Washington law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Washington official source linked on this page or consult a licensed Washington attorney.

How does Washington § 78.56.090 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Washington can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Washington.