§ 47.60.820. Design-build ferries — Phase three.

Phase three consists of the submittal and evaluation of bids and the award of the contract to the successful proposer for the final design and construction of the auto ferries, as follows:
(1) The department shall request bids for detailed design and construction of the vessels after completion of the review of technical proposals in phase two. The department will review detailed design drawings in phase three for conformity with the technical proposals submitted in phase two. In no case may the department's review replace the builder's responsibility to deliver a product meeting the phase two technical proposal. The department may only consider bids from selected proposers that have qualified to bid by submitting technical proposals that have been approved by the department.
(2) Each qualified proposer must submit its total bid price for all vessels, including certification that the bid is based upon its approved technical proposal and the request for proposals.
(3) Bids constitute an offer and remain open for ninety days from the date of the bid opening. A deposit in cash, certified check, cashier's check, or surety bond in an amount specified in the request for proposals must accompany each bid and no bid may be considered unless the deposit is enclosed.
(4) The department shall evaluate the submitted bids. Upon completing the bid evaluation, the department may select the responsive and responsible proposer that offers the lowest total fixed price bid for all vessels.
(5) The department may waive informalities in the proposal and bid process, accept a bid from the lowest responsive and responsible proposer, reject any or all bids, republish, and revise or cancel the request for proposals to serve the best interests of the department.
(6) The department may:
(a) Award the contract to the proposer that has been selected as the responsive and responsible proposer that has submitted the lowest total fixed price bid;
(b) If a contract cannot be signed with the apparent successful proposer, award the contract to the next lowest responsive and responsible proposer; or
(c) If necessary, repeat this procedure with each responsive and responsible proposer in order of rank until the list of those proposers has been exhausted.
(7) If the department awards a contract to a proposer under this section, and the proposer fails to enter into the contract and furnish satisfactory contract security as required by chapter 39.08 RCW within twenty days from the date of award, its deposit is forfeited to the state and will be deposited by the state treasurer to the credit of the Puget Sound capital construction account. Upon the execution of a ferry design and construction contract all proposal deposits will be returned.
(8) The department may provide an honorarium to reimburse each unsuccessful phase three proposer for a portion of its technical proposal preparation costs at a preset, fixed amount to be specified in the request for proposals. If the department rejects all bids, the department may provide the honoraria to all phase three proposers that submitted bids.
(9)(a) To accommodate change orders on a fixed price contract, the department shall request that the legislative appropriation for any auto ferry construction project include a contingency in the following amounts:
(i) For the first vessel in any class of vessels designed to be powered by liquefied natural gas, the contingency may be no more than ten percent of the contract price;
(ii) For all other vessels, the contingency may be no more than five percent of the contract price.
(b) The contingency required by this subsection (9) must be identified in the funding request to the legislature and held in reserve until the office of financial management approves the expenditure.
[ 2015 3rd sp.s. c 14 s 6; 2001 c 226 s 9.]

Notes

Effective date—2015 3rd sp.s. c 14: See note following RCW 47.60.005.
Findings—Purpose—2001 c 226: See note following RCW 47.20.780.

Frequently Asked Questions About Washington § 47.60.820

What does Revised Code of Washington § 47.60.820 cover?

Section 47.60.820 ("Design-build ferries — Phase three.") is part of the Revised Code of Washington, the codified statutory law of Washington. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Washington § 47.60.820?

A common citation format is "Revised Code of Washington § 47.60.820" (Washington). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Washington law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Washington official source linked on this page or consult a licensed Washington attorney.

How does Washington § 47.60.820 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Washington can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Washington.