Full text of Washington Revised Code of Washington § 39.10.410 — General contractor/construction manager procedure — Subcontract agreements., with citation guidance and answers to common questions.
§ 39.10.410. General contractor/construction manager procedure — Subcontract agreements.
Subcontract agreements used by the general contractor/construction manager shall not:
(1) Delegate, restrict, or assign the general contractor/construction manager's implied duty not to hinder or delay the subcontractor. Nothing in this subsection (1) prohibits the general contractor/construction manager from requiring subcontractors not to hinder or delay the work of the general contractor/construction manager or other subcontractors and to hold subcontractors responsible for such damages;
(2) Delegate, restrict, or assign the general contractor/construction manager's authority to resolve subcontractor conflicts. The general contractor/construction manager may delegate or assign coordination of specific elements of the work, including: (a) The coordination of shop drawings among subcontractors; (b) the coordination among subcontractors in ceiling spaces and mechanical rooms; and (c) the coordination of a subcontractor's lower tier subcontractors. Nothing in this subsection prohibits the general contractor/construction manager from imposing a duty on its subcontractors to cooperate with the general contractor/construction manager and other subcontractors in the coordination of the work;
(3) Restrict the subcontractor's right to damages for changes to the construction schedule or work to the extent that the delay or disruption is caused by the general contractor/construction manager or entities acting for it. The general contractor/construction manager may require the subcontractor to provide notice that rescheduling or resequencing will result in delays or additional costs;
(4) Require the subcontractor to bear the cost of trade damage repair except to the extent the subcontractor is responsible for the damage. Nothing in this subsection (4) precludes the general contractor/construction manager from requiring the subcontractor to take reasonable steps to protect the subcontractor's work from trade damage; or
(5) Require the subcontractor to execute progress payment applications that waive claims for additional time or compensation or bond or retainage rights as a condition of receipt of progress payment, except to the extent the subcontractor has received or will receive payment. Nothing in this section precludes the general contractor/construction manager from requiring the subcontractor to provide notice of claims for additional time or compensation as a condition precedent to right of recovery or to execute a full and final release, including a waiver of bond and retainage rights, as a condition of final payment.
Notes
Sunset Act application: See note following chapter digest.
Source: official Washington text · Last verified 2026-08-27
Frequently Asked Questions About Washington § 39.10.410
What does Revised Code of Washington § 39.10.410 cover?
Section 39.10.410 ("General contractor/construction manager procedure — Subcontract agreements.") is part of the Revised Code of Washington, the codified statutory law of Washington. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Washington § 39.10.410?
A common citation format is "Revised Code of Washington § 39.10.410" (Washington). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Washington law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Washington official source linked on this page or consult a licensed Washington attorney.
How does Washington § 39.10.410 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Washington can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Washington.