Washington § 60.28.021 - Excess over lien claims paid to contractor.

Full text of Washington Revised Code of Washington § 60.28.021 — Excess over lien claims paid to contractor., with citation guidance and answers to common questions.

§ 60.28.021. Excess over lien claims paid to contractor.

After the expiration of the forty-five day period for giving notice of lien provided in RCW 60.28.011(2), and after receipt of the certificates of the department of revenue, the employment security department, and the department of labor and industries, and the public body is satisfied that the taxes certified as due or to become due by the department of revenue, the employment security department, and the department of labor and industries are discharged, and the claims of material suppliers and laborers who have filed their claims, together with a sum sufficient to defray the cost of foreclosing the liens of such claims, and to pay attorneys' fees, have been paid, the public body may withhold from the remaining retained amounts for claims the public body may have against the contractor and shall pay the balance, if any, to the contractor the fund retained by it or release to the contractor the securities and bonds held in escrow.
If such taxes have not been discharged or the claims, expenses, and fees have not been paid, the public body shall either retain in its fund, or in an interest bearing account, or retain in escrow, at the option of the contractor, an amount equal to such unpaid taxes and unpaid claims together with a sum sufficient to defray the costs and attorney fees incurred in foreclosing the lien of such claims, and shall pay, or release from escrow, the remainder to the contractor.
[ 2009 c 432 s 6; 2007 c 218 s 94; 1992 c 223 s 3.]

Notes

Report—2009 c 432: See RCW 18.27.800.
Intent—Finding—2007 c 218: See note following RCW 41.08.020.
Effective date—1992 c 223: See note following RCW 39.76.011.
Waiver of rights, construction—Application—1992 c 223: See RCW 39.04.900 and 39.04.901.

Source: official Washington text · Last verified 2026-08-27

Frequently Asked Questions About Washington § 60.28.021

What does Revised Code of Washington § 60.28.021 cover?

Section 60.28.021 ("Excess over lien claims paid to contractor.") is part of the Revised Code of Washington, the codified statutory law of Washington. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Washington § 60.28.021?

A common citation format is "Revised Code of Washington § 60.28.021" (Washington). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Washington law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Washington official source linked on this page or consult a licensed Washington attorney.

How does Washington § 60.28.021 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Washington can advise on how this section applies to you. Contact your state or local bar association for a referral.