Washington § 80.50.100 - Recommendations to governor — Expedited processing — Approval or rejection of certification — Reconsideration.

Full text of Washington Revised Code of Washington § 80.50.100 — Recommendations to governor — Expedited processing — Approval or rejection of certification — Reconsideration., with citation guidance and answers to common questions.

§ 80.50.100. Recommendations to governor — Expedited processing — Approval or rejection of certification — Reconsideration.

(1)(a) The council shall report to the governor its recommendations as to the approval or rejection of an application for certification within twelve months of receipt by the council of an application deemed complete by the director, or such later time as is mutually agreed by the council and the applicant.
(b) The council shall review and consider comments received during the application process in making its recommendation.
(c) In the case of an application filed prior to December 31, 2025, for certification of an energy facility proposed for construction, modification, or expansion for the purpose of providing generating facilities that meet the requirements of RCW 80.80.040 and are located in a county with a coal-fired electric generation facility subject to RCW 80.80.040(3)(c), the council shall expedite the processing of the application pursuant to RCW 80.50.075 and shall report its recommendations to the governor within one hundred eighty days of receipt by the council of such an application, or a later time as is mutually agreed by the council and the applicant.
(2) If the council recommends approval of an application for certification, it shall also submit a draft certification agreement with the report. The council shall include conditions in the draft certification agreement to implement the provisions of this chapter including, but not limited to, conditions to protect state, local governmental, or community interests, or overburdened communities as defined in RCW 70A.02.010 affected by the construction or operation of the facility, and conditions designed to recognize the purpose of laws or ordinances, or rules or regulations promulgated thereunder, that are preempted or superseded pursuant to RCW 80.50.110 as now or hereafter amended.
(3)(a) Within 60 days of receipt of the council's report the governor shall take one of the following actions:
(i) Approve the application and execute the draft certification agreement; or
(ii) Reject the application; or
(iii) Direct the council to reconsider certain aspects of the draft certification agreement.
(b) The council shall reconsider such aspects of the draft certification agreement by reviewing the existing record of the application or, as necessary, by reopening the adjudicative proceeding for the purposes of receiving additional evidence. Such reconsideration shall be conducted expeditiously. The council shall resubmit the draft certification to the governor incorporating any amendments deemed necessary upon reconsideration. Within 60 days of receipt of such draft certification agreement, the governor shall either approve the application and execute the certification agreement or reject the application. The certification agreement shall be binding upon execution by the governor and the applicant.
(4) The rejection of an application for certification by the governor shall be final as to that application but shall not preclude submission of a subsequent application for the same site on the basis of changed conditions or new information.
[ 2022 c 183 s 10; 2011 c 180 s 109; 1989 c 175 s 174; 1977 ex.s. c 371 s 8; 1975-'76 2nd ex.s. c 108 s 36; 1970 ex.s. c 45 s 10.]

Notes

Effective date—2022 c 183: See note following RCW 80.50.010.
Findings—Purpose—2011 c 180: See note following RCW 80.80.010.
Effective date—1989 c 175: See note following RCW 34.05.010.
Severability—Effective date—1975-'76 2nd ex.s. c 108: See notes following RCW 43.21F.010.

Source: official Washington text · Last verified 2026-08-27

Frequently Asked Questions About Washington § 80.50.100

What does Revised Code of Washington § 80.50.100 cover?

Section 80.50.100 ("Recommendations to governor — Expedited processing — Approval or rejection of certification — Reconsideration.") is part of the Revised Code of Washington, the codified statutory law of Washington. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Washington § 80.50.100?

A common citation format is "Revised Code of Washington § 80.50.100" (Washington). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Washington law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Washington official source linked on this page or consult a licensed Washington attorney.

How does Washington § 80.50.100 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Washington can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Washington.