Virginia § 10.1-610.1 - Monitoring progress of work
Full text of Virginia Code of Virginia § 10.1-610.1 — Monitoring progress of work, with citation guidance and answers to common questions.
§ 10.1-610.1. Monitoring progress of work
A. During the maintenance, construction, or alteration of any dam or reservoir, the Department shall make periodic inspections for the purpose of securing conformity with the approved plans and specifications. The Department shall require the owner to perform at his expense such work or tests as necessary to obtain information sufficient to enable the Department to determine whether conformity with the approved plans and specifications is being secured.
B. If, after any inspections, investigations, or examinations, or at any time as the work progresses, or at any time prior to issuance of a certificate of approval, it is found by the Director that project modifications or changes are necessary to ensure conformity with the approved plans and specifications, the Director may issue an administrative order to the owner to comply with the plans and specifications. Within 15 calendar days after being served by personal service or by mail with a copy of an order issued pursuant to this section, any owner shall have the right to petition the Board for a hearing. A timely filed petition shall stay the effect of the administrative order. The hearing shall be conducted before the Board or a designated member of the Board pursuant to § 2.2-4019. The Board shall have the authority to affirm, modify, amend, or cancel the administrative order. Any owner aggrieved by a decision of the Board after a hearing shall have the right to judicial review of the final Board decision pursuant to the provisions of the Administrative Process Act (§ 2.2-4000 et seq.).
C. Following the Board hearing, subject to judicial review of the final decision of the Board, if conditions are revealed that will not permit the construction of a safe dam or reservoir, the certificate of approval may be revoked. As part of the revocation, the Board may compel the owner to remove the incomplete structure sufficiently to eliminate any safety hazard to life or property.
2006, c. 30.
Source: official Virginia text · Last verified 2026-08-27
Frequently Asked Questions About Virginia § 10.1-610.1
What does Code of Virginia § 10.1-610.1 cover?
Section 10.1-610.1 ("Monitoring progress of work") is part of the Code of Virginia, the codified statutory law of Virginia. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Virginia § 10.1-610.1?
A common citation format is "Code of Virginia § 10.1-610.1" (Virginia). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Virginia law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Virginia official source linked on this page or consult a licensed Virginia attorney.
How does Virginia § 10.1-610.1 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Virginia can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Virginia.