§ 10g. Annual report; Transportation Program; advancements, cancellations, and delays

  • (a) Proposed Transportation Program. The Agency of Transportation shall annually present to the General Assembly for adoption
    a multiyear Transportation Program covering the same number of years as the Statewide
    Transportation Improvement Program (STIP), consisting of the recommended budget for
    all Agency activities for the ensuing fiscal year and projected spending levels for
    all Agency activities for the following fiscal years. The Program shall include a
    description and year-by-year breakdown of recommended and projected funding of all
    projects proposed to be funded within the time period of the STIP and, in addition,
    a description of all projects that are not recommended for funding in the first fiscal
    year of the proposed Program but that are scheduled for construction during the time
    period covered by the STIP. The Program shall be consistent with the planning process
    established by 1988 Acts and Resolves No. 200, as codified in 3 V.S.A. chapter 67 and 24 V.S.A. chapter 117, the statements of policy set forth in sections 10b-10f of this title, and the long-range systems plan, corridor studies, and project priorities developed
    through the capital planning process under section 10i of this title. (b) Projected spending. Projected spending in future fiscal years shall be based on revenue estimates as follows: (1) with respect to State funds, on the consensus forecast for Transportation Fund revenue
    adopted pursuant to 32 V.S.A. § 305a and for later years on other consensus or Executive Branch estimates of Transportation
    Fund revenues; and (2) with respect to federal funds, on such federal regulations that apply to the development
    of the STIP. (c) Systemwide performance measures. The Program proposed by the Agency shall include systemwide performance measures developed
    by the Agency to describe the condition of the Vermont transportation network. The
    Program shall discuss the background and utility of the performance measures, track
    the performance measures over time, and, where appropriate, recommend the setting
    of targets for the performance measures. (d) [Repealed.] (e) Prior expenditures and appropriations carried forward. (1) The Agency’s annual Transportation Program shall include a separate report summarizing
    with respect to the most recently ended fiscal year: (A) all expenditures of funds by source; and (B) all unexpended appropriations of transportation funds and TIB funds that have been
    carried forward from the previous fiscal year to the ensuing fiscal year. (2) The summary shall identify expenditures and carry forwards for each program category
    included in the proposed annual Transportation Program as adopted for the closed fiscal
    year in question and such other information as the Agency deems appropriate. (f) Adopted Transportation Program. Each year following adoption of a Transportation Program under this section, the
    Agency shall prepare and make available to the public the Transportation Program adopted
    by the General Assembly. The resulting document shall be entered in the permanent
    records of the Agency and shall constitute the State’s official Transportation Program. (g) Project updates. The Agency’s annual proposed Transportation Program shall include project updates
    referencing this section and listing the following: (1) all proposed projects in the Program that would be new to the State Transportation
    Program; (2) all projects for which total estimated costs have increased by more than $5,000,000.00
    from the estimate in the adopted Transportation Program for the prior fiscal year
    or by more than 75 percent from the estimate in the adopted Transportation Program
    for the prior fiscal year; (3) all projects for which the total estimated costs have, for the first time, increased
    by more than $10,000,000.00 from the Preliminary Plan estimate or by more than 100
    percent from the Preliminary Plan estimate; and (4) all projects funded for construction in the prior fiscal year’s adopted Transportation
    Program that are no longer funded in the proposed Transportation Program submitted
    to the General Assembly, the projected costs for such projects in the prior fiscal
    year’s adopted Transportation Program, and the total costs incurred over the life
    of each such project. (h) Project delays; emergency and safety issues; additional funding; cancellations. (1) If capital projects in the Transportation Program are delayed because of unanticipated
    problems with permitting, right-of-way acquisition, construction, local concern, or
    availability of federal or State funds, the Secretary is authorized to advance other
    projects in the adopted Transportation Program for the current fiscal year. (2) The Secretary is further authorized to undertake projects to resolve emergency or
    safety issues that are not included in the adopted Transportation Program for the
    current fiscal year. Upon authorizing a project to resolve an emergency or safety
    issue, the Secretary shall give prompt notice of the decision and action taken to
    the Joint Fiscal Office and to the House and Senate Committees on Transportation when
    the General Assembly is in session and to the Joint Transportation Oversight Committee,
    the Joint Fiscal Office, and the Joint Fiscal Committee when the General Assembly
    is not in session. (3) If a project in the adopted Transportation Program for the current fiscal year requires
    additional funding to maintain the schedule in the adopted Transportation Program
    for the current fiscal year, the Agency is authorized to allocate the necessary resources.
    However, the Secretary shall not delay or suspend work on projects in the adopted
    Transportation Program for the current fiscal year to reallocate funding for other
    projects except when other funding options are not available. In such case, the Secretary
    shall notify the Joint Transportation Oversight Committee, the Joint Fiscal Office,
    and the Joint Fiscal Committee when the General Assembly is not in session and the
    House and Senate Committees on Transportation and the Joint Fiscal Office when the
    General Assembly is in session. With respect to projects in the approved Transportation
    Program, the Secretary shall notify the regional planning commission for the district
    where the affected project is located, the municipality where the affected project
    is located, the legislators for the district where the affected project is located,
    the House and Senate Committees on Transportation, and the Joint Fiscal Office of
    any change that likely will affect the fiscal year in which the project is planned
    to go to construction. (4) No project shall be canceled without the approval of the General Assembly, except
    that the Agency may cancel a municipal project upon the request or concurrence of
    the municipality, provided that notice of the cancellation is included in the Agency’s
    annual proposed Transportation Program. (i) Economic development proposals. For the purpose of enabling the State, without delay, to take advantage of economic
    development proposals that increase jobs for Vermonters, a transportation project
    certified by the Governor as essential to the economic infrastructure of the State
    economy, or a local economy, may, if approval is required by law, be approved for
    construction by a committee comprising the Joint Fiscal Committee meeting with the
    chairs of the House and Senate Committees on Transportation or their designees without
    explicit project authorization through an adopted Transportation Program. (j) Plan for advancing projects. The Agency of Transportation, in coordination with the Agency of Natural Resources
    and the Division for Historic Preservation, shall prepare and implement a plan for
    advancing projects contained in the adopted Transportation Program for the current
    fiscal year. The plan shall include the assignment of a project manager from the Agency
    of Transportation for each project. The Agency of Transportation, the Agency of Natural
    Resources, and the Division for Historic Preservation shall set forth provisions for
    expediting the permitting process and establishing a means for evaluating each project
    during concept design planning if more than one agency is involved to determine whether
    it should be advanced or deleted from the Program. (k) Definition. As used in subsection (h) of this section, “emergency or safety issues” means: (1) serious damage to a transportation facility caused by a natural disaster over a wide
    area, such as a flood, hurricane, earthquake, severe storm, or landslide; (2) catastrophic or imminent catastrophic failure of a transportation facility from any
    cause; (3) any condition identified by the Secretary as hazardous to the traveling public; or (4) any condition evidenced by fatalities or a high incidence of crashes. (l) Numerical grading system; priority rating. The Agency shall develop a numerical grading system to assign a priority rating to
    all Program Development Paving, Program Development Roadway, Program Development Safety
    and Traffic Operations, Program Development State and Interstate Bridge, Town Highway
    Bridge, and Bridge Maintenance projects. The rating system shall consist of two separate,
    additive components as follows: (1) One component shall be limited to asset management- and performance-based factors
    that are objective and quantifiable and shall consider the following: (A) the existing safety conditions in the project area and the impact of the project on
    improving safety conditions; (B) the average, seasonal, peak, and nonpeak volume of traffic in the project area, including
    the proportion of traffic volume relative to total volume in the region, and the impact
    of the project on congestion and mobility conditions in the region; (C) the availability, accessibility, and usability of alternative routes; (D) the impact of the project on future maintenance and reconstruction costs; (E) the relative priority assigned to the project by the relevant regional planning commission;
    and (F) the resilience of the transportation infrastructure to floods and other extreme weather
    events. (2) The second component of the priority rating system shall consider the following factors: (A) the importance of the transportation infrastructure as a factor in the local, regional,
    or State economy; and (B) the importance of the transportation infrastructure in the health, social, and cultural
    life of the surrounding communities. (3) The priority rating system for Program Development Roadway projects shall award as
    bonus points an amount equal to 10 percent of the total base possible rating points
    to projects within a designated downtown development district established pursuant
    to 24 V.S.A. § 2793. (m) Inclusion of priority rating. The annual proposed Transportation Program shall include an individual priority rating
    pursuant to subsection (l) of this section for each highway paving, roadway, safety and traffic operations,
    and bridge project in the Program along with a description of the system and methodology
    used to assign the ratings. (n) Development and evaluation projects; delays. The Agency’s annual proposed Transportation Program shall include a project-by-project
    description in each program of all proposed spending of funds for the development
    and evaluation of projects. These funds shall be reserved to the identified projects
    subject to the discretion of the Secretary to reallocate funds to other projects within
    the program when it is determined that the scheduled expenditure of the identified
    funds will be delayed due to permitting, local decision making, the availability of
    federal or State funds, or other unanticipated problems. (o) Year of first inclusion. For projects initially included in a Transportation Program adopted after January
    1, 2006, the Agency’s proposed Transportation Program prepared pursuant to subsection
    (a) of this section and the adopted Transportation Program prepared pursuant to subsection
    (f) of this section shall include the year in which the projects were first included
    in an adopted Transportation Program. (p) Lamoille Valley Rail Trail. The Agency shall include the annual maintenance required for the Lamoille Valley
    Rail Trail (LVRT), running from Swanton to St. Johnsbury, in the Transportation Program
    it presents to the General Assembly under subsection (a) of this section. The proposed
    authorization for the maintenance of the LVRT shall be sufficient to cover: (1) maintenance and repair or replacement of any bridges along the LVRT; (2) maintenance and repair of the fencing along the LVRT and any leased lines; (3) maintenance and repair of the stormwater systems for the LVRT; (4) any large-scale surface maintenance required due to dangerous conditions along the
    LVRT or compromise of the rail bed of the LVRT, or both; (5) resolution of any unauthorized encroachments related to the rail bed, but not the
    recreational use of the LVRT; and (6) any other maintenance obligations required of the Agency under a memorandum of understanding
    entered into regarding the maintenance of the LVRT. (Added 1989, No. 121, § 6, eff. June 22, 1989; amended 1989, No. 246 (Adj. Sess.), § 38; 1991, No. 175 (Adj. Sess.), § 25b, eff. May 15, 1992; 1993, No. 89, § 22; 1993, No. 89, § 22; 1993, No. 172 (Adj. Sess.), § 16; 1995, No. 60, § 20, eff. April 25, 1995; 1995, No. 183 (Adj. Sess.), § 17, eff. May 22, 1996; 1997, No. 144 (Adj. Sess.), § 12a, eff. April 27, 1998; 2001, No. 64, § 9, eff. June 16, 2001; 2003, No. 160 (Adj. Sess.), § 30, eff. June 9, 2004; 2005, No. 80, §§ 53, 60; 2005, No. 175 (Adj. Sess.), §§ 46, 47; 2007, No. 75, §§ 35(a), 38; 2007, No. 164 (Adj. Sess.), §§ 61, 62; 2009, No. 123 (Adj. Sess.), § 22; 2011, No. 62, § 36, eff. Jan. 1, 2012; 2011, No. 153 (Adj. Sess.), § 29; 2015, No. 11, § 25; 2015, No. 158 (Adj. Sess.), §§ 18, 20, 21; 2017, No. 38, § 13; 2019, No. 59, § 9; 2021, No. 55, § 13; 2021, No. 105 (Adj. Sess.), § 349, eff. July 1, 2022; 2023, No. 148 (Adj. Sess.), § 12, eff. July 1, 2024.)

Source: official Vermont text · Last verified 2026-08-27

Frequently Asked Questions About Vermont § 10g

What does Vermont Statutes Online § 10g cover?

Section 10g ("Annual report; Transportation Program; advancements, cancellations, and delays") is part of the Vermont Statutes Online, the codified statutory law of Vermont. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Vermont § 10g?

A common citation format is "Vermont Statutes Online § 10g" (Vermont). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Vermont law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Vermont official source linked on this page or consult a licensed Vermont attorney.

How does Vermont § 10g apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Vermont can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification