| (4) |
| (a) | Except as provided in Subsection (4)(b), the executive director may only use fund money to pay:
| (i) | the costs of maintenance, construction, reconstruction, or renovation to state and federal highways prioritized by the Transportation Commission through the prioritization process for new transportation capacity projects adopted under Section 72-1-304; |
| (ii) | the costs of maintenance, construction, reconstruction, or renovation to the highway projects described in Subsections 63B-18-401(2), (3), and (4); |
| (iii) | subject to Subsection (9), costs of corridor preservation, as that term is defined in Section 72-5-401; |
| (iv) | principal, interest, and issuance costs of bonds authorized by Section 63B-18-401 minus the costs paid from the County of the First Class Highway Projects Fund in accordance with Subsection 72-2-121(4)(e); |
| (v) | for a fiscal year beginning on or after July 1, 2013, to transfer to the 2010 Salt Lake County Revenue Bond Sinking Fund created by Section 72-2-121.3 the amount certified by Salt Lake County in accordance with Subsection 72-2-121.3(4)(c) as necessary to pay the debt service on $30,000,000 of the revenue bonds issued by Salt Lake County; |
| (vi) | principal, interest, and issuance costs of bonds authorized by Section 63B-16-101 for projects prioritized in accordance with Section 72-2-125; |
| (vii) | for fiscal year 2015-16 only, to transfer $25,000,000 to the County of the First Class Highway Projects Fund created in Section 72-2-121 to be used for the purposes described in Section 72-2-121; |
| (viii) | if a political subdivision provides a contribution equal to or greater than 40% of the costs needed for construction, reconstruction, or renovation of paved pedestrian or paved nonmotorized transportation for projects that:
| (A) | mitigate traffic congestion on the state highway system; |
| (B) | are part of an active transportation plan approved by the department; and |
| (C) | are prioritized by the commission through the prioritization process for new transportation capacity projects adopted under Section 72-1-304; |
|
| (ix) | $705,000,000 for the costs of right-of-way acquisition, construction, reconstruction, or renovation of or improvement to the following projects:
| (A) | the connector road between Main Street and 1600 North in the city of Vineyard; |
| (B) | Geneva Road from University Parkway to 1800 South; |
| (C) | the SR-97 interchange at 5600 South on I-15; |
| (D) | subject to Subsection (4)(d), two lanes on U-111 from Herriman Parkway to South Jordan Parkway; |
| (E) | widening I-15 between mileposts 10 and 13 and the interchange at milepost 11; |
| (F) | improvements to 1600 North in Orem from 1200 West to State Street; |
| (G) | widening I-15 between mileposts 6 and 8; |
| (H) | widening 1600 South from Main Street in the city of Spanish Fork to SR-51; |
| (I) | widening US 6 from Sheep Creek to Mill Fork between mileposts 195 and 197 in Spanish Fork Canyon; |
| (J) | I-15 northbound between mileposts 43 and 56; |
| (K) | a passing lane on SR-132 between mileposts 41.1 and 43.7 between mileposts 43 and 45.1; |
| (L) | east Zion SR-9 improvements; |
| (N) | an environmental study on Foothill Boulevard in the city of Saratoga Springs; |
| (O) | using funds allocated in this Subsection (4)(a)(ix), and other sources of funds, for construction of an interchange on Bangerter Highway at 13400 South; and |
| (P) | an environmental impact study for Kimball Junction in Summit County; |
|
| (x) | $28,000,000 as pass-through funds, to be distributed as necessary to pay project costs based upon a statement of cash flow that the local jurisdiction where the project is located provides to the department demonstrating the need for money for the project, for the following projects in the following amounts:
| (A) | $5,000,000 for Payson Main Street repair and replacement; |
| (B) | $8,000,000 for a Bluffdale 14600 South railroad bypass; |
| (C) | $5,000,000 for improvements to 4700 South in Taylorsville; and |
| (D) | $10,000,000 for improvements to the west side frontage roads adjacent to U.S. 40 between mile markers 7 and 10; |
|
| (xi) | $13,000,000 as pass-through funds to Spanish Fork for the costs of right-of-way acquisition, construction, reconstruction, or renovation to connect Fingerhut Road over the railroad and to U.S. Highway 6; |
| (xii) | for a fiscal year beginning on July 1, 2025, only, as pass-through funds from revenue deposited into the fund in accordance with Section 59-12-103, for the following projects:
| (A) | $3,000,000 for the department to perform an environmental study for the I-15 Salem and Benjamin project; and |
| (B) | $2,000,000, as pass-through funds, to Kane County for the Coral Pink Sand Dunes Road project; |
|
| (xiii) | for a fiscal year beginning on July 1, 2025, up to $250,000,000 for the costs of right-of-way acquisition and construction for improvements on and connections to SR-89 and surrounding transportation facilities in a county of the first class; and |
| (xiv) | for grants awarded under Part 5, Affordable Housing Infrastructure Grants, subject to repayment to the fund from bond proceeds described in Section 63B-34-101, if the executive director finds that providing the grant money will not delay a project prioritized by the commission. |
|
| (b) | The executive director may use fund money to exchange for an equal or greater amount of federal transportation funds to be used as provided in Subsection (4)(a). |
| (c) | Subject to legislative appropriation, money in the fund may be used for the operation of a state highway, including enforcement of state motor vehicle and traffic laws, if the state highway was constructed, reconstructed, or renovated using money from the fund. |
| (d) |
| (i) | Construction related to the project described in Subsection (4)(a)(ix)(D) may not commence until a right-of-way not owned by a federal agency that is required for the realignment and extension of U-111, as described in the department's 2023 environmental study related to the project, is dedicated to the department. |
| (ii) | Notwithstanding Subsection (4)(d)(i), if a right-of-way is not dedicated for the project as described in Subsection (4)(d)(i) on or before October 1, 2024, the department may proceed with the project, except that the project will be limited to two lanes on U-111 from Herriman Parkway to 11800 South. |
|
| (e) | For a fiscal year beginning on July 1, 2026, the Division of Finance shall transfer $50,000,000 of the revenue deposited into the fund to the Convention Center Reserves Restricted Account created in Section 72-2-136. |
|