Each applicant for a certificate shall file in the office of the commission evidence as required by the commission to show that the applicant has received or is in the process of obtaining the required consent, franchise, or permit of the proper county, city, municipal, or other public authority. |
| (ii) |
If the applicant is in the process of obtaining the required consent, franchise, or permit, a certificate shall be conditioned upon:
| (A) |
receipt of the consent, franchise, or permit within the time period the commission may direct; and |
| (B) |
the filing of such evidence of the receipt of the consent, franchise, or permit as the commission may require. |
|
|
| (b) |
Each applicant, except an interlocal entity defined in Section 11-13-103, shall also file in the office of the commission a statement that any proposed line, plant, or system will not conflict with or adversely affect the operations of any existing certificated fixed public utility which supplies the same product or service to the public and that it will not constitute an extension into the territory certificated to the existing fixed public utility. |
| (c) |
The commission may, after a hearing:
| (i) |
issue the certificate as requested; |
| (ii) |
refuse to issue the certificate; or |
| (iii) |
issue the certificate for the construction of a portion only of the contemplated line, plant, or system, or extension thereof, or for the partial exercise only of the right or privilege. |
|
| (d) |
The commission may attach to the exercise of the rights granted by the certificate the terms and conditions as in its judgment public convenience and necessity may require. |
| (e) |
| (i) |
If a public utility desires to exercise a right or privilege under a franchise or permit which it contemplates securing but which has not yet been granted to it, the public utility may apply to the commission for an order preliminary to the issue of the certificate. |
| (ii) |
The commission may make an order declaring that it will upon application, under rules and regulations as it may prescribe, issue the desired certificate upon terms and conditions as it may designate after the public utility has obtained the contemplated franchise or permit. |
| (iii) |
Upon presentation to the commission of evidence satisfactory to it that the franchise or permit has been secured by the public utility, the commission shall issue the certificate. |
|
|