§ 8353. General requirements for exemptions
(a) Use of mixtures or fluidized bed combustion not feasible
Except in the case of an exemption under section 8352(b), (f), or (i) of this title, the Secretary may grant a permanent exemption for a powerplant under this part only—
(1) if the applicant has demonstrated that the use of a mixture of natural gas or petroleum and coal (or other alternate fuels), for which an exemption under section 8352(b) of this title would be available, is not economically or technically feasible; and
(2) if the Secretary has not made a finding that the use of a method of fluidized bed combustion of coal or an alternate fuel is economically and technically feasible.
(b) No alternative power supply in case of a powerplant
(1) In the case of an exemption under section 8352(b) or (g) of this title, the Secretary may not grant an exemption for an existing powerplant unless he finds that the petitioner has demonstrated that there is no alternative supply of electric power which is available within a reasonable distance at a reasonable cost without impairing short-run or long-run reliability of service and which can be obtained by the petitioner, despite reasonable good faith efforts.
(2) The Secretary shall forward a copy of any such petition to the Federal Energy Regulatory Commission promptly after it is filed with the Secretary and shall consult with the Commission before making any finding on such petition under paragraph (l).
(Pub. L. 95–620, title III, §313, Nov. 9, 1978, 92 Stat. 3313; Pub. L. 100–42, §1(c)(10), (13), May 21, 1987, 101 Stat. 313.)
Editorial Notes
Amendments
1987—Subsec. (a). Pub. L. 100–42, §1(c)(13), struck out "or installation" after "powerplant" in introductory provisions.
Pub. L. 100–42, §1(c)(10), which directed the substitution of "or (i)" for "(i), or (j)" was executed by making the substitution for "(i) or (j)" to reflect the probable intent of Congress.
Statutory Notes and Related Subsidiaries
Exemption for Certain Electric Powerplants as Effective Prior to 180 Days After November 9, 1978
For effectiveness of exemption for certain electric powerplants as prior to 180 days after Nov. 9, 1978, see section 902(a) of Pub. L. 95–620, set out as a note under section 8301 of this title.
About This Section
42 U.S.C. § 8353 is part of Title 42 of the United States Code. The United States Code is the official codification of federal statutes maintained by the Office of the Law Revision Counsel of the U.S. House of Representatives. Congress amends the Code through new public laws, which are eventually incorporated into the relevant title.
This section may be cited in legal writing as 42 U.S.C. § 8353. For the most current official text, including any recent amendments, use the official source links below. Do not rely on this page as the sole authority for legal citation or litigation.
How to Read This Statute
Statutes are organized by title, chapter, section, and subsection. Pay attention to words like "shall," "may," "and," and "or," because they determine whether a requirement is mandatory or permissive and whether multiple conditions must all be met. Historical notes and amendments often appear at the end of a section.
Using This Page
This page is intended for research and educational use. Lawyers, students, journalists, and compliance professionals can use it as a starting point, but should always verify the current text through an official government source before relying on it for legal advice, filings, or compliance decisions.