Us Code § 8322 - Permanent exemptions

Full text of Us Code United States Code § 8322 — Permanent exemptions, with citation guidance and answers to common questions.

§ 8322. Permanent exemptions

(a) Permanent exemption due to lack of alternate fuel supply, site limitations, environmental requirements, or adequate capital

(1) After consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary shall, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum, if he finds that the petitioner has demonstrated that despite diligent good faith efforts—

(A) it is likely that an adequate and reliable supply of coal or other alternate fuel of the quality necessary to conform with design and operational requirements for use as a primary energy source (i) will not be available within the first 10 years of the useful life of the powerplant, or (ii) will not be available at a cost (taking into account associated facilities for the transportation and use of such fuel) which, based upon the best practicable estimates, does not substantially exceed the cost, as determined by rule by the Secretary, of the fuel that would be used as a primary energy source during the useful life of the powerplant involved;

(B) one or more site limitations exist which would not permit the location or operation of such powerplant using coal or any other alternate fuel as a primary energy source;

(C) the prohibitions of part A could not be satisfied without violating applicable environmental requirements; or

(D) the required use of coal or any other alternate fuel would not allow the petitioner to obtain adequate capital for the financing of such powerplant.


(2) The demonstration required to be made by a petitioner under paragraph (1) shall be made with respect to the site of such powerplant and reasonable alternative sites.

(b) Permanent exemption due to certain State or local requirements

After consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary may, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum, if he finds that the petitioner has demonstrated that—

(1) with respect to the proposed site of the powerplant, the construction or operation of such a facility using coal or any other alternate fuel is infeasible because of a State or local requirement (other than a building code or a nuisance or zoning law);

(2) there is no reasonable alternative site for such powerplant which meets the criteria set forth in subsection (a)(1)(A) through (D); and

(3) the granting of the exemption would be in the public interest and would be consistent with the purposes of this chapter.

(c) Permanent exemption for cogeneration

After consideration of a petition (and comments thereon) for an exemption from one or more of the prohibitions of part A for a cogeneration facility, the Secretary may, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum, if he—

(1) finds that the petitioner has demonstrated that economic and other benefits of cogeneration are unobtainable unless petroleum or natural gas, or both, are used in such facility, and

(2) includes in the final order a statement of the basis for such finding.

(d) Permanent exemption for certain mixtures containing natural gas or petroleum

After consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary shall, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum, if he finds that the petitioner has demonstrated that—

(1) the powerplant uses, or proposes to use, a mixture of petroleum or natural gas and coal or another alternate fuel as a primary energy source; and

(2) the amount of the petroleum or natural gas used in such mixture will not exceed the minimum percentage of the total Btu heat input of the primary energy sources of such powerplant needed to maintain reliability of operation of such powerplant consistent with maintaining a reasonable level of fuel efficiency, as determined in accordance with rules prescribed by the Secretary.

(e) Permanent exemption for emergency purposes

After consideration of a petition (and comments thereon) for an exemption from one or more of the prohibitions of part A for a powerplant, the Secretary shall, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum, if he finds that the petitioner has demonstrated that such powerplant will be maintained and operated only for emergency purposes (as defined by rule by the Secretary).

(f) Permanent exemption for powerplants necessary to maintain reliability of service

After consideration of a petition (and comments thereon) for an exemption for a powerplant from one or more of the prohibitions of part A, the Secretary may, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum if he finds that the petitioner has demonstrated that—

(1) such exemption is necessary to prevent impairment of reliability of service, and

(2) the petitioner, despite diligent good faith efforts, is not able to make the demonstration necessary to obtain an exemption under subsection (a) or (b) in the time required to prevent such impairment of service.

(Pub. L. 95–620, title II, §212, Nov. 9, 1978, 92 Stat. 3300; Pub. L. 100–42, §1(c)(6), May 21, 1987, 101 Stat. 312.)


Editorial Notes

References in Text

This chapter, referred to in subsec. (b)(3), was in the original "this Act", meaning Pub. L. 95–620, Nov. 9, 1978, 92 Stat. 3289, known as the Powerplant and Industrial Fuel Use Act of 1978, which is classified principally to this chapter. For complete classification of this Act to the Code, see Short Title note set out under section 8301 of this title and Tables.

Amendments

1987—Subsec. (a)(1). Pub. L. 100–42, §1(c)(6)(A)–(C), substituted "from" for "or installation from one or more of" in introductory provisions, substituted "the fuel that would be used" for "using imported petroleum" and struck out "or installation" after "powerplant" wherever appearing in subpar. (A), and struck out "or installation" after "powerplant" in subpars. (B) and (D).

Subsec. (a)(2). Pub. L. 100–42, §1(c)(1)(D), struck out "—

"(A) in the case of a new major fuel-burning installation, be made with respect to the site of such installation proposed by the petitioner; and

"(B) in the case of a new electric powerplant,"

after "paragraph (1) shall".

Subsec. (a)(3). Pub. L. 100–42, §1(c)(6)(E), struck out par. (3) which read as follows: "Notwithstanding the preceding provisions of this subsection, a powerplant which has been granted an exemption under subsection (h) may not be granted an exemption under this subsection."

Subsec. (b). Pub. L. 100–42, §1(c)(6)(A), (B), (F), in introductory provisions substituted "from" for "or installation from one or more of", in par. (1) struck out "or installation" after "powerplant", and in par. (2) struck out "in the case of a powerplant," after "(2)".

Subsec. (d). Pub. L. 100–42, §1(c)(6)(A), (B), (G), struck out "(1)" before "After consideration of", substituted "from" for "installation from one or more of" in introductory provisions, redesignated subpars. (A) and (B) of former par. (1) as pars. (1) and (2), respectively, struck out "or installation" after "powerplant" wherever appearing in such pars., and struck out former par. (2) which read as follows: "In the case of a new major fuel-burning installation, the percentage determined by the Secretary under subparagraph (B) of paragraph (1) shall not be less than 25 percent."

Subsec. (e). Pub. L. 100–42, §1(c)(6)(B), struck out "or installation" after "powerplant" wherever appearing.

Subsec. (g). Pub. L. 100–42, §1(c)(6)(H), struck out subsec. (g) which related to issuance, by order of Secretary of Energy, of permanent exemptions for use of natural gas or petroleum for peakload powerplants.

Subsec. (h). Pub. L. 100–42, §1(c)(6)(H), struck out subsec. (h) which related to issuance, by order of Secretary of Energy, of permanent exemptions for use of petroleum for intermediate load powerplants.

Subsec. (i). Pub. L. 100–42, §1(c)(6)(H), struck out subsec. (i) which related to issuance, by order of Secretary of Energy, of permanent exemptions for use of natural gas or petroleum for installations based upon product or process requirements.

Subsec. (j). Pub. L. 100–42, §1(c)(6)(H), struck out subsec. (j) which related to issuance, by order of Secretary of Energy, of permanent exemptions for use of natural gas or petroleum for installations necessary to meet scheduled equipment outages.


Statutory Notes and Related Subsidiaries

Exemption for Certain Electric Powerplants as Effective Prior to 180 Days After November 9, 1978

For effectiveness of exemption for certain electric powerplants as prior to 180 days after Nov. 9, 1978, see section 902(a) of Pub. L. 95–620, set out as a note under section 8301 of this title.

About This Section

42 U.S.C. § 8322 is part of Title 42 of the United States Code. The United States Code is the official codification of federal statutes maintained by the Office of the Law Revision Counsel of the U.S. House of Representatives. Congress amends the Code through new public laws, which are eventually incorporated into the relevant title.

This section may be cited in legal writing as 42 U.S.C. § 8322. For the most current official text, including any recent amendments, use the official source links below. Do not rely on this page as the sole authority for legal citation or litigation.

How to Read This Statute

Statutes are organized by title, chapter, section, and subsection. Pay attention to words like "shall," "may," "and," and "or," because they determine whether a requirement is mandatory or permissive and whether multiple conditions must all be met. Historical notes and amendments often appear at the end of a section.

Using This Page

This page is intended for research and educational use. Lawyers, students, journalists, and compliance professionals can use it as a starting point, but should always verify the current text through an official government source before relying on it for legal advice, filings, or compliance decisions.

Sources

Frequently Asked Questions About Us Code § 8322

What does United States Code § 8322 cover?

Section 8322 ("Permanent exemptions") is part of the United States Code, the codified statutory law of Us Code. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Us Code § 8322?

A common citation format is "United States Code § 8322" (Us Code). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Us Code law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Us Code official source linked on this page or consult a licensed Us Code attorney.

How does Us Code § 8322 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Us Code can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Us Code.