§ 2773. Independent acquisition project reviews of capital assets acquisition projects
(a) Reviews
The appropriate head shall ensure that an independent entity conducts reviews of each capital assets acquisition project as the project moves toward the approval of each of critical decision 0, critical decision 1, and critical decision 2 in the acquisition process.
(b) Pre-critical decision 1 reviews
In addition to any other matters, with respect to each review of a capital assets acquisition project under subsection (a) that has not reached critical decision 1 approval in the acquisition process, such review shall include—
(1) a review using best practices of the analysis of alternatives for the project; and
(2) identification of any deficiencies in such analysis of alternatives for the appropriate head to address.
(c) Independent entities
The appropriate head shall ensure that each review of a capital assets acquisition project under subsection (a) is conducted by an independent entity with the appropriate expertise with respect to the project and the stage in the acquisition process of the project.
(d) Definitions
In this section:
(1) The term "acquisition process" means the acquisition process for a project, as defined in Department of Energy Order 413.3B (relating to project management and project management for the acquisition of capital assets), or a successor order.
(2) The term "appropriate head" means—
(A) the Administrator, with respect to capital assets acquisition projects of the Administration; and
(B) the Assistant Secretary of Energy for Environmental Management, with respect to capital assets acquisition projects of the Office of Environmental Management.
(3) The term "capital assets acquisition project" means a project—
(A) the total project cost of which is more than $500,000,000; and
(B) that is covered by Department of Energy Order 413.3B, or a successor order, for the acquisition of capital assets for atomic energy defense activities.
(Pub. L. 107–314, div. D, title XLVII, §4733, as added Pub. L. 114–328, div. C, title XXXI, §3111(a), Dec. 23, 2016, 130 Stat. 2755; amended Pub. L. 116–92, div. C, title XXXI, §3139(b)(8), Dec. 20, 2019, 133 Stat. 1963.)
Editorial Notes
Amendments
2019—Subsec. (d)(3)(B). Pub. L. 116–92 substituted "413.3B" for "413.3".
SUBCHAPTER VIII—ADMINISTRATIVE MATTERS
Part A—Contracts
About This Section
50 U.S.C. § 2773 is part of Title 50 of the United States Code. The United States Code is the official codification of federal statutes maintained by the Office of the Law Revision Counsel of the U.S. House of Representatives. Congress amends the Code through new public laws, which are eventually incorporated into the relevant title.
This section may be cited in legal writing as 50 U.S.C. § 2773. For the most current official text, including any recent amendments, use the official source links below. Do not rely on this page as the sole authority for legal citation or litigation.
How to Read This Statute
Statutes are organized by title, chapter, section, and subsection. Pay attention to words like "shall," "may," "and," and "or," because they determine whether a requirement is mandatory or permissive and whether multiple conditions must all be met. Historical notes and amendments often appear at the end of a section.
Using This Page
This page is intended for research and educational use. Lawyers, students, journalists, and compliance professionals can use it as a starting point, but should always verify the current text through an official government source before relying on it for legal advice, filings, or compliance decisions.