§ 10365. Hydroelectric power assessment

(a) Duty of Secretary of Energy

The Secretary of Energy, in consultation with the Administrator of each Federal Power Marketing Administration, shall assess each effect of, and risk resulting from, global climate change with respect to water supplies that are required for the generation of hydroelectric power at each Federal water project that is applicable to a Federal Power Marketing Administration.

(b) Access to appropriate data

(1) In general

In carrying out each assessment under subsection (a), the Secretary of Energy shall consult with the United States Geological Survey, the National Oceanic and Atmospheric Administration, the program, and each appropriate State water resource agency, to ensure that the Secretary of Energy has access to the best available scientific information with respect to presently observed impacts and projected future impacts of global climate change on water supplies that are used to produce hydroelectric power.

(2) Access to data for certain assessments

In carrying out each assessment under subsection (a), with respect to the Bonneville Power Administration and the Western Area Power Administration, the Secretary of Energy shall consult with the Commissioner to access data and other information that—

(A) is collected by the Commissioner; and

(B) the Secretary of Energy determines to be necessary for the conduct of the assessment.

(c) Report

Not later than 2 years after March 30, 2009, and every 5 years thereafter, the Secretary of Energy shall submit to the appropriate committees of Congress a report that describes—

(1) each effect of, and risk resulting from, global climate change with respect to—

(A) water supplies used for hydroelectric power generation; and

(B) power supplies marketed by each Federal Power Marketing Administration, pursuant to—

(i) long-term power contracts;

(ii) contingent capacity contracts; and

(iii) short-term sales; and


(2) each recommendation of the Administrator of each Federal Power Marketing Administration relating to any change in any operation or contracting practice of each Federal Power Marketing Administration to address each effect and risk described in paragraph (1), including the use of purchased power to meet long-term commitments of each Federal Power Marketing Administration.

(d) Authority

The Secretary of Energy may enter into contracts, grants, or other agreements with appropriate entities to carry out this section.

(e) Costs

(1) Nonreimbursable

Any costs incurred by the Secretary of Energy in carrying out this section shall be nonreimbursable.

(2) PMA costs

Each Federal Power Marketing Administration shall incur costs in carrying out this section only to the extent that appropriated funds are provided by the Secretary of Energy for that purpose.

(f) Authorization of appropriations

There are authorized to be appropriated such sums as are necessary to carry out this section for each of fiscal years 2009 through 2023, to remain available until expended.

(Pub. L. 111–11, title IX, §9505, Mar. 30, 2009, 123 Stat. 1336.)

About This Section

42 U.S.C. § 10365 is part of Title 42 of the United States Code. The United States Code is the official codification of federal statutes maintained by the Office of the Law Revision Counsel of the U.S. House of Representatives. Congress amends the Code through new public laws, which are eventually incorporated into the relevant title.

This section may be cited in legal writing as 42 U.S.C. § 10365. For the most current official text, including any recent amendments, use the official source links below. Do not rely on this page as the sole authority for legal citation or litigation.

How to Read This Statute

Statutes are organized by title, chapter, section, and subsection. Pay attention to words like "shall," "may," "and," and "or," because they determine whether a requirement is mandatory or permissive and whether multiple conditions must all be met. Historical notes and amendments often appear at the end of a section.

Using This Page

This page is intended for research and educational use. Lawyers, students, journalists, and compliance professionals can use it as a starting point, but should always verify the current text through an official government source before relying on it for legal advice, filings, or compliance decisions.

Sources

Frequently Asked Questions About Us Code § 10365

What does United States Code § 10365 cover?

Section 10365 ("Hydroelectric power assessment") is part of the United States Code, the codified statutory law of Us Code. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Us Code § 10365?

A common citation format is "United States Code § 10365" (Us Code). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Us Code law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Us Code official source linked on this page or consult a licensed Us Code attorney.

How does Us Code § 10365 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Us Code can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Us Code.