§ LG.252.048. CHANGE ORDERS
CHANGE ORDERS. (a) If changes in plans or specifications are necessary after the performance of the contract is begun or if it is necessary to decrease or increase the quantity of work to be performed or of materials, equipment, or supplies to be furnished, the governing body of the municipality may approve change orders making the changes. (b) The total contract price may not be increased because of the changes unless additional money for increased costs is appropriated for that purpose from available funds or is provided for by the authorization of the issuance of time warrants. (c) If a change order involves a decrease or an increase of $50,000 or less, the governing body may grant general authority to an administrative official of the municipality to approve the change orders. (c-1) If a change order for a public works contract in a municipality with a population of 240,000 or more involves a decrease or an increase of $100,000 or less, or a lesser amount as provided by ordinance, the governing body of the municipality may grant general authority to an administrative official of the municipality to approve the change order. (d) The original contract price may not be increased under this section by more than 25 percent. The original contract price may not be decreased under this section by more than 25 percent without the consent of the contractor. (e) This section applies only to a contract awarded through a competitive procedure as required by Section 252.021 . Acts 1987, 70th Leg., ch. 149, Sec. 1, eff. Sept. 1, 1987. Amended by Acts 1995, 74th Leg., ch. 706, Sec. 1, eff. Sept. 1, 1995; Acts 1995, 74th Leg., ch. 746, Sec. 2, eff. Aug. 28, 1995. Amended by: Acts 2011, 82nd Leg., R.S., Ch. 479 (H.B. 679 ), Sec. 1, eff. June 17, 2011. Acts 2011, 82nd Leg., R.S., Ch. 1129 (H.B. 628 ), Sec. 2.09, eff. September 1, 2011. Acts 2013, 83rd Leg., R.S., Ch. 1127 (H.B. 1050 ), Sec. 7, eff. September 1, 2013. Acts 2013, 83rd Leg., R.S., Ch. 1356 (S.B. 1430 ), Sec. 2, eff. June 14, 2013. Acts 2023, 88th Leg., R.S., Ch. 406 (H.B. 1440 ), Sec. 1, eff. September 1, 2023.
Frequently Asked Questions About Texas § LG.252.048
What does The Texas Constitution § LG.252.048 cover?
Section LG.252.048 ("CHANGE ORDERS") is part of the The Texas Constitution, the codified statutory law of Texas. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Texas § LG.252.048?
A common citation format is "The Texas Constitution § LG.252.048" (Texas). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Texas law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Texas official source linked on this page or consult a licensed Texas attorney.
How does Texas § LG.252.048 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Texas can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Texas.