§ 5-18B-19. Amendment or change order to existing contract.
Any amendment or change order to an existing contract for construction, reconstruction, or remodeling of a public improvement does not need to be bid if:
(1) The contract contains unit prices for the same type or class of work;
(2) The change or extra work is necessitated by circumstances related to soils, utilities, or unknown conditions directly affecting the performance of the work that were not reasonably foreseeable at the time the underlying contract was let and the change or extra work is necessary to the completion of the public improvement; or
(3) The sum of the proposed amendment or change order plus the sum of all other prior unbid amendments or change orders, exclusive of change orders issued under subdivisions (1) and (2) of this section, does not exceed the following:
(a) For contracts not more than five hundred thousand dollars, the greater of twenty-five thousand dollars or fifteen percent of the base contract;
(b) For contracts exceeding five hundred thousand dollars but not more than two million five hundred thousand dollars, the greater of seventy-five thousand dollars or ten percent of the base contract; and
(c) For contracts exceeding two million five hundred thousand dollars, the greater of two hundred fifty thousand dollars or five percent of the base contract.
Source: SL 2010, ch 31, § 58.
Source: official South Dakota text · Last verified 2026-08-27
Frequently Asked Questions About South Dakota § 5-18B-19
What does South Dakota Codified Laws § 5-18B-19 cover?
Section 5-18B-19 ("Amendment or change order to existing contract.") is part of the South Dakota Codified Laws, the codified statutory law of South Dakota. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite South Dakota § 5-18B-19?
A common citation format is "South Dakota Codified Laws § 5-18B-19" (South Dakota). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of South Dakota law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the South Dakota official source linked on this page or consult a licensed South Dakota attorney.
How does South Dakota § 5-18B-19 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in South Dakota can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in South Dakota.