South Dakota § 49-41B-25 - Permit for wind or solar energy facility--Time for complete findings by commission--Notice of decision.

Full text of South Dakota South Dakota Codified Laws § 49-41B-25 — Permit for wind or solar energy facility--Time for complete findings by commission--Notice of decision., with citation guidance and answers to common questions.

§ 49-41B-25. Permit for wind or solar energy facility--Time for complete findings by commission--Notice of decision.

Within nine months of receipt of the initial application for a permit for the construction of a wind energy facility or solar energy facility, the commission shall make complete findings, and render a decision, regarding whether a permit should be granted, denied, or granted upon such terms, conditions, or modifications of the construction, operation, or maintenance as the commission determines are appropriate. In the decision, the commission shall find that the construction of the facility meets all requirements of this chapter. Notice of the commission's decision shall be given to the applicant and to parties to the hearing within ten days following the decision.

Source: SL 1977, ch 390, § 19; SL 2005, ch 250, § 3; SL 2015, ch 235, § 3; SL 2019, ch 200, § 9.

Source: official South Dakota text · Last verified 2026-08-27

Frequently Asked Questions About South Dakota § 49-41B-25

What does South Dakota Codified Laws § 49-41B-25 cover?

Section 49-41B-25 ("Permit for wind or solar energy facility--Time for complete findings by commission--Notice of decision.") is part of the South Dakota Codified Laws, the codified statutory law of South Dakota. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite South Dakota § 49-41B-25?

A common citation format is "South Dakota Codified Laws § 49-41B-25" (South Dakota). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of South Dakota law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the South Dakota official source linked on this page or consult a licensed South Dakota attorney.

How does South Dakota § 49-41B-25 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in South Dakota can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in South Dakota.