Oklahoma § 61-225 - Suspension or termination of construction contract Payment
Full text of Oklahoma Oklahoma Statutes § 61-225 — Suspension or termination of construction contract Payment, with citation guidance and answers to common questions.
§ 61-225. Suspension or termination of construction contract Payment
A. Any prime contractor that performs work under a construction
contract may suspend performance of the work or may terminate a
construction contract if the prime contractor is not properly paid
within forty-nine (49) calendar days of the date that the
corresponding proper invoice is submitted. Written notice must be
received by the owner at least seven (7) calendar days before any
such intended suspension or termination.
B. A prime contractor or any entity that suspends performance
due to the suspension of a prime contractor, is not required to
Oklahoma Statutes - Title 61. Public Buildings and Public Works
furnish further performance until such entity is paid for the full
amount, less retainage, of work performed, material supplied, or
services rendered, together with any costs incurred for
demobilization, mobilization and other costs attributable to delay
of the work resulting from the shutdown and start-up of a project.
C. Any entity that suspends performance of the work or
terminates a construction contract for nonpayment under this act
shall not be held in breach of the construction contract.
D. If the owner delays in making payments to the prime
contractor, any agreed-upon schedule or completion date and their
resulting penalties, damages, bonuses, or rewards shall be extended
by the same amount of calendar days that payments were late.
E. If a payment to a prime contractor is received later than as
specified in this act, that prime contractor shall be entitled to
receive interest pursuant to Section 41.4b of Title 62 of the
Oklahoma Statutes. If the prime contractor has already paid a
subcontractor, then no interest is due and owing to the
subcontractor. If interest is paid to a prime contractor as
provided herein, then any subsequent timely payment made to a
subcontractor shall bear interest at the same rate paid to the prime
contractor. If a prime contractor fails to timely pay a
subcontractor, such payment to a subcontractor shall bear interest
at the rate of one and one-half percent (1 1/2%) per month.
Added by Laws 2004, c. 256, § 5, eff. Nov. 1, 2004. Amended by Laws
2004, c. 425, § 4, eff. July 1, 2004; Laws 2005, c. 92, § 3, eff.
Nov. 1, 2005. Renumbered from Title 15, § 625 by Laws 2005, c. 92,
§ 6, eff. Nov. 1, 2005.
Source: official Oklahoma text · Last verified 2026-08-27
Frequently Asked Questions About Oklahoma § 61-225
What does Oklahoma Statutes § 61-225 cover?
Section 61-225 ("Suspension or termination of construction contract Payment") is part of the Oklahoma Statutes, the codified statutory law of Oklahoma. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Oklahoma § 61-225?
A common citation format is "Oklahoma Statutes § 61-225" (Oklahoma). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Oklahoma law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Oklahoma official source linked on this page or consult a licensed Oklahoma attorney.
How does Oklahoma § 61-225 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Oklahoma can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Oklahoma.