Oklahoma § 19-880 - Subdistrict sewers - Petition - Profiles, plans and

Full text of Oklahoma Oklahoma Statutes § 19-880 — Subdistrict sewers - Petition - Profiles, plans and, with citation guidance and answers to common questions.

§ 19-880. Subdistrict sewers - Petition - Profiles, plans and

specifications - Contracts.

Whenever such district sewer or sewers shall have been

authorized, the said board of directors shall then proceed to employ

a registered professional engineer licensed in the State of

Oklahoma, and cause to be prepared profiles, plans and

Oklahoma Statutes - Title 19. Counties and County Officers

specifications for the work, together with a complete estimate of

the cost. Upon the completion of such plans and specifications and

their adoption by the said board of directors, they shall advertise

for sealed bids for the performance of such work for at least ten

(10) days, if published in a daily newspaper, or at least two (2)

successive weeks if published in a weekly newspaper. In either

case, such newspaper must be one of general circulation within the

district and such notice may contain any reasonable conditions to be

imposed by said board of directors with reference to the letting of

such contracts and shall require the giving of a good and sufficient

bond for the faithful execution of work and the performance of the

contract and for the protection of the district and all property

owners against any loss or damage by the negligent execution of such

work. Such notice shall also advise all parties interested that

they may appear and protest against such proposed improvement or any

part thereof. At the time and place specified in the notice the

board of directors shall award the contract to the lowest and best

bidder for the work, which contract shall in no case exceed the

aggregate estimate of cost submitted with the plans and

specifications and shall be subject to the right of the board of

directors to reject any and all bids and to readvertise for other

bids, when none of the same is, in their judgment, satisfactory.

Added by Laws 1947, p. 221, § 10, emerg. eff. May 16, 1947. Amended

by Laws 1949, p. 182, § 5, emerg. eff. May 12, 1949.

Source: official Oklahoma text · Last verified 2026-08-27

Frequently Asked Questions About Oklahoma § 19-880

What does Oklahoma Statutes § 19-880 cover?

Section 19-880 ("Subdistrict sewers - Petition - Profiles, plans and") is part of the Oklahoma Statutes, the codified statutory law of Oklahoma. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Oklahoma § 19-880?

A common citation format is "Oklahoma Statutes § 19-880" (Oklahoma). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Oklahoma law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Oklahoma official source linked on this page or consult a licensed Oklahoma attorney.

How does Oklahoma § 19-880 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Oklahoma can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Oklahoma.