(A)(1) No operator shall conduct a coal mining operation without a permit for the operation
issued by the chief of the division of mineral resources management. (2) All permits issued pursuant to this chapter shall be issued for a term not to exceed
five years, except that, if the applicant demonstrates that a specified longer term
is reasonably needed to allow the applicant to obtain necessary financing for equipment
and the opening of the operation and if the application is full and complete for the
specified longer term, the chief may grant a permit for the longer term. A successor in interest to a permittee who applies for a new permit within thirty
days after succeeding to the interest and who is able to obtain the performance security
of the original permittee may continue coal mining and reclamation operations according
to the approved mining and reclamation plan of the original permittee until the successor's
application is granted or denied. (3) A permit shall terminate if the permittee has not commenced the coal mining operations
covered by the permit within three years after the issuance of the permit, except
that the chief may grant reasonable extensions of the time upon a showing that the
extensions are necessary by reason of litigation precluding the commencement or threatening
substantial economic loss to the permittee or by reason of conditions beyond the control
and without the fault or negligence of the permittee, and except that with respect
to coal to be mined for use in a synthetic fuel facility or specified major electric
generating facility, the permittee shall be deemed to have commenced coal mining operations
at the time construction of the synthetic fuel or generating facility is initiated. (4)(a) Any permit issued pursuant to this chapter shall carry with it the right of successive
renewal upon expiration with respect to areas within the boundaries of the permit. The holders of the permit may apply for renewal and the renewal shall be issued
unless the chief determines by written findings, subsequent to fulfillment of the
public notice requirements of this section and section 1513.071 of the Revised Code through demonstrations by opponents of renewal or otherwise, that one or more of
the following circumstances exists: (i) The terms and conditions of the existing permit are not being satisfactorily met. (ii) The present coal mining and reclamation operation is not in compliance with the environmental
protection standards of this chapter. (iii) The renewal requested substantially jeopardizes the operator's continuing responsibilities
on existing permit areas. (iv) The applicant has not provided evidence that the performance security in effect for
the operation will continue in effect for any renewal requested in the application. (v) Any additional, revised, or updated information required by the chief has not been
provided. Prior to the approval of any renewal of a permit, the chief shall provide notice
to the appropriate public authorities as prescribed by rule of the chief. (b) If an application for renewal of a valid permit includes a proposal to extend the
mining operation beyond the boundaries authorized in the existing permit, the portion
of the application for renewal of a valid permit that addresses any new land areas
shall be subject to the full standards applicable to new applications under this chapter. (c) A permit renewal shall be for a term not to exceed the period of the original permit
established by this chapter. Application for permit renewal shall be made at least one hundred twenty days prior
to the expiration of the valid permit. (5) A permit issued pursuant to this chapter does not eliminate the requirements for
obtaining a permit to install or modify a disposal system or any part thereof or to
discharge sewage, industrial waste, or other wastes into the waters of the state in
accordance with Chapter 6111. of the Revised Code. (B)(1) The permit application shall be submitted in a manner satisfactory to the chief and
shall contain, among other things, all of the following: (a) The names and addresses of all of the following: (i) The permit applicant; (ii) Every legal owner of record of the property, surface and mineral, to be mined; (iii) The holders of record of any leasehold interest in the property; (iv) Any purchaser of record of the property under a real estate contract; (v) The operator if different from the applicant; (vi) If any of these are business entities other than a single proprietor, the names and
addresses of the principals, officers, and statutory agent for service of process. (b) The names and addresses of the owners of record of all surface and subsurface areas
adjacent to any part of the permit area; (c) A statement of any current or previous coal mining permits in the United States held
by the applicant, the permit identification, and any pending applications; (d) If the applicant is a partnership, corporation, association, or other business entity,
the following where applicable: the names and addresses of every officer, partner,
director, or person performing a function similar to a director, of the applicant,
the name and address of any person owning, of record, ten per cent or more of any
class of voting stock of the applicant, a list of all names under which the applicant,
partner, or principal shareholder previously operated a coal mining operation within
the United States within the five-year period preceding the date of submission of
the application, and a list of the person or persons primarily responsible for ensuring
that the applicant complies with the requirements of this chapter and rules adopted
pursuant thereto while mining and reclaiming under the permit; (e) A statement of whether the applicant, any subsidiary, affiliate, or persons controlled
by or under common control with the applicant, any partner if the applicant is a partnership,
any officer, principal shareholder, or director if the applicant is a corporation,
or any other person who has a right to control or in fact controls the management
of the applicant or the selection of officers, directors, or managers of the applicant: (i) Has ever held a federal or state coal mining permit that in the five-year period
prior to the date of submission of the application has been suspended or revoked or
has had a coal mining bond, performance security, or similar security deposited in
lieu of bond forfeited and, if so, a brief explanation of the facts involved; (ii) Has been an officer, partner, director, principal shareholder, or person having the
right to control or has in fact controlled the management of or the selection of officers,
directors, or managers of a business entity that has had a coal mining or surface
mining permit that in the five-year period prior to the date of submission of the
application has been suspended or revoked or has had a coal mining or surface mining
bond, performance security, or similar security deposited in lieu of bond forfeited
and, if so, a brief explanation of the facts involved. (f) A copy of the applicant's advertisement to be published in a newspaper of general
circulation in the locality of the proposed site at least once a week for four successive
weeks, which shall include the ownership of the proposed mine, a description of the
exact location and boundaries of the proposed site sufficient to make the proposed
operation readily identifiable by local residents, and the location where the application
is available for public inspection; (g) A description of the type and method of coal mining operation that exists or is proposed,
the engineering techniques proposed or used, and the equipment used or proposed to
be used; (h) The anticipated or actual starting and termination dates of each phase of the mining
operation and number of acres of land to be affected; (i) An accurate map or plan, to an appropriate scale, clearly showing the land to be
affected, the land upon which the applicant has the legal right to enter and commence
coal mining operations, and the land for which the applicant will acquire the legal
right to enter and commence coal mining operations during the term of the permit,
copies of those documents upon which is based the applicant's legal right to enter
and commence coal mining operations or a notarized statement describing the applicant's
legal right to enter and commence coal mining operations, and a statement whether
that right is the subject of pending litigation. This chapter does not authorize the chief to adjudicate property title disputes. (j) The name of the watershed and location of the surface stream or tributary into which
drainage from the operation will be discharged; (k) A determination of the probable hydrologic consequences of the mining and reclamation
operations, both on and off the mine site, with respect to the hydrologic regime,
providing information on the quantity and quality of water in surface and ground water
systems including the dissolved and suspended solids under seasonal flow conditions
and the collection of sufficient data for the mine site and surrounding areas so that
an assessment can be made by the chief of the probable cumulative impacts of all anticipated
mining in the area upon the hydrology of the area and particularly upon water availability,
but this determination shall not be required until hydrologic information of the general
area prior to mining is made available from an appropriate federal or state agency;
however, the permit shall not be approved until the information is available and
is incorporated into the application; (l) When requested by the chief, the climatological factors that are peculiar to the
locality of the land to be affected, including the average seasonal precipitation,
the average direction and velocity of prevailing winds, and the seasonal temperature
ranges; (m) Accurate maps prepared by or under the direction of and certified by a qualified
registered professional engineer, registered surveyor, or licensed landscape architect
to an appropriate scale clearly showing all types of information set forth on topographical
maps of the United States geological survey of a scale of not more than four hundred
feet to the inch, including all artificial features and significant known archeological
sites. The map, among other things specified by the chief, shall show all boundaries of
the land to be affected, the boundary lines and names of present owners of record
of all surface areas abutting the permit area, and the location of all buildings within
one thousand feet of the permit area. (n)(i) Cross-section maps or plans of the land to be affected including the actual area
to be mined, prepared by or under the direction of and certified by a qualified registered
professional engineer or certified professional geologist with assistance from experts
in related fields such as hydrology, hydrogeology, geology, and landscape architecture,
showing pertinent elevations and locations of test borings or core samplings and depicting
the following information: the nature and depth of the various strata of overburden;
the nature and thickness of any coal or rider seam above the coal seam to be mined;
the nature of the stratum immediately beneath the coal seam to be mined; all mineral
crop lines and the strike and dip of the coal to be mined within the area to be affected;
existing or previous coal mining limits; the location and extent of known workings
of any underground mines, including mine openings to the surface; the location of
spoil, waste, or refuse areas and topsoil preservation areas; the location of all
impoundments for waste or erosion control; any settling or water treatment facility;
constructed or natural drainways and the location of any discharges to any surface
body of water on the land to be affected or adjacent thereto; profiles at appropriate
cross sections of the anticipated final surface configuration that will be achieved
pursuant to the operator's proposed reclamation plan; the location of subsurface
water, if encountered; the location and quality of aquifers; and the estimated elevation
of the water table. Registered surveyors shall be allowed to perform all plans, maps, and certifications
under this chapter as they are authorized under Chapter 4733. of the Revised Code. (ii) A statement of the quality and locations of subsurface water. The chief shall provide by rule the number of locations to be sampled, frequency
of collection, and parameters to be analyzed to obtain the statement required. (o) A statement of the results of test borings or core samplings from the permit area,
including logs of the drill holes, the thickness of the coal seam found, an analysis
of the chemical properties of the coal, the sulfur content of any coal seam, chemical
analysis of potentially acid or toxic forming sections of the overburden, and chemical
analysis of the stratum lying immediately underneath the coal to be mined, except
that this division may be waived by the chief with respect to the specific application
by a written determination that its requirements are unnecessary. If the test borings or core samplings from the permit area indicate the existence
of potentially acid forming or toxic forming quantities of sulfur in the coal or overburden
to be disturbed by mining, the application also shall include a statement of the acid
generating potential and the acid neutralizing potential of the rock strata to be
disturbed as calculated in accordance with the calculation method established under section 1513.075 of the Revised Code or with another calculation method. (p) For those lands in the permit application that a reconnaissance inspection suggests
may be prime farmlands, a soil survey shall be made or obtained according to standards
established by the secretary of the United States department of agriculture in order
to confirm the exact location of the prime farmlands, if any; (q) A certificate issued by an insurance company authorized to do business in this state
certifying that the applicant has a public liability insurance policy in force for
the coal mining and reclamation operations for which the permit is sought or evidence
that the applicant has satisfied other state self-insurance requirements. The policy shall provide for personal injury and property damage protection in an
amount adequate to compensate any persons damaged as a result of coal mining and reclamation
operations, including the use of explosives, and entitled to compensation under the
applicable provisions of state law. The policy shall be maintained in effect during the term of the permit or any renewal,
including the length of all reclamation operations. The insurance company shall give prompt notice to the permittee and the chief if
the public liability insurance policy lapses for any reason including the nonpayment
of insurance premiums. Upon the lapse of the policy, the chief may suspend the permit and all other outstanding
permits until proper insurance coverage is obtained. (r) The business telephone number of the applicant; (s) If the applicant seeks an authorization under division (E)(7) of this section to
conduct coal mining and reclamation operations on areas to be covered by the permit
that were affected by coal mining operations before August 3, 1977, that have resulted
in continuing water pollution from or on the previously mined areas, such additional
information pertaining to those previously mined areas as may be required by the chief,
including, without limitation, maps, plans, cross sections, data necessary to determine
existing water quality from or on those areas with respect to pH, iron, and manganese,
and a pollution abatement plan that may improve water quality from or on those areas
with respect to pH, iron, and manganese. (2) Information pertaining to coal seams, test borings, core samplings, or soil samples
as required by this section shall be made available by the chief to any person with
an interest that is or may be adversely affected, except that information that pertains
only to the analysis of the chemical and physical properties of the coal, excluding
information regarding mineral or elemental content that is potentially toxic in the
environment, shall be kept confidential and not made a matter of public record. (3)(a) If the chief finds that the probable total annual production at all locations of
any operator will not exceed three hundred thousand tons, the following activities,
upon the written request of the operator in connection with a permit application,
shall be performed by a qualified public or private laboratory or another public or
private qualified entity designated by the chief, and the cost of the activities shall
be assumed by the chief, provided that sufficient moneys for such assistance are available: (i) The determination of probable hydrologic consequences required under division (B)(1)(k)
of this section; (ii) The development of cross-section maps and plans required under division (B)(1)(n)(i)
of this section; (iii) The geologic drilling and statement of results of test borings and core samplings
required under division (B)(1)(o) of this section; (iv) The collection of archaeological information required under division (B)(1)(m) of
this section and any other archaeological and historical information required by the
chief, and the preparation of plans necessitated thereby; (v) Pre-blast surveys required under division (B)(5) of section 1513.161 of the Revised Code ; (vi) The collection of site-specific resource information and production of protection
and enhancement plans for fish and wildlife habitats and other environmental values
required by the chief under this chapter. (b) A coal operator that has received assistance under division (B)(3)(a) of this section
shall reimburse the chief for the cost of the services rendered if the chief finds
that the operator's actual and attributed annual production of coal for all locations
exceeds three hundred thousand tons during the twelve months immediately following
the date on which the operator was issued a coal mining and reclamation permit. (4) Each applicant for a permit shall submit to the chief as part of the permit application
a reclamation plan that meets the requirements of this chapter. (5) Each applicant for a coal mining and reclamation permit shall file a copy of the
application for a permit, excluding that information pertaining to the coal seam itself,
for public inspection with the county recorder or an appropriate public office approved
by the chief in the county where the mining is proposed to occur. (6) Each applicant for a coal mining and reclamation permit shall submit to the chief
as part of the permit application a blasting plan that describes the procedures and
standards by which the operator will comply with section 1513.161 of the Revised Code . (C) Each reclamation plan submitted as part of a permit application shall include, in
the detail necessary to demonstrate that reclamation required by this chapter can
be accomplished and in the detail necessary for the chief to determine the estimated
cost of reclamation if the reclamation has to be performed by the division of mineral
resources management in the event of forfeiture of the performance security by the
applicant, a statement of: (1) The identification of the lands subject to coal mining operations over the estimated
life of those operations and the size, sequence, and timing of the subareas for which
it is anticipated that individual permits for mining will be sought; (2) The condition of the land to be covered by the permit prior to any mining, including
all of the following: (a) The uses existing at the time of the application and, if the land has a history of
previous mining, the uses that preceded any mining; (b) The capability of the land prior to any mining to support a variety of uses, giving
consideration to soil and foundation characteristics, topography, and vegetative cover
and, if applicable, a soil survey prepared pursuant to division (B)(1)(p) of this
section; (c) The productivity of the land prior to mining, including appropriate classification
as prime farmlands as well as the average yield of food, fiber, forage, or wood products
obtained from the land under high levels of management. (3) The use that is proposed to be made of the land following reclamation, including
information regarding the utility and capacity of the reclaimed land to support a
variety of alternative uses, the relationship of the proposed use to existing land
use policies and plans, and the comments of any owner of the land and state and local
governments or agencies thereof that would have to initiate, implement, approve, or
authorize the proposed use of the land following reclamation; (4) A detailed description of how the proposed postmining land use is to be achieved
and the necessary support activities that may be needed to achieve the proposed land
use; (5) The engineering techniques proposed to be used in mining and reclamation and a description
of the major equipment; a plan for the control of surface water drainage and of water
accumulation; a plan, where appropriate, for backfilling, soil stabilization, and
compacting, grading, and appropriate revegetation; a plan for soil reconstruction,
replacement, and stabilization, pursuant to the performance standards in section 1513.16 of the Revised Code , for those food, forage, and forest lands identified in that section; and a statement
as to how the permittee plans to comply with each of the requirements set out in section 1513.16 of the Revised Code ; (6) A description of the means by which the utilization and conservation of the solid
fuel resource being recovered will be maximized so that reaffecting the land in the
future can be minimized; (7) A detailed estimated timetable for the accomplishment of each major step in the reclamation
plan; (8) A description of the degree to which the coal mining and reclamation operations are
consistent with surface owner plans and applicable state and local land use plans
and programs; (9) The steps to be taken to comply with applicable air and water quality laws and regulations
and any applicable health and safety standards; (10) A description of the degree to which the reclamation plan is consistent with local
physical, environmental, and climatological conditions; (11) A description of all lands, interests in lands, or options on such interests held
by the applicant or pending bids on interests in lands by the applicant, which lands
are contiguous to the area to be covered by the permit; (12) The results of test borings that the applicant has made at the area to be covered
by the permit, or other equivalent information and data in a form satisfactory to
the chief, including the location of subsurface water, and an analysis of the chemical
properties, including acid forming properties of the mineral and overburden; except
that information that pertains only to the analysis of the chemical and physical properties
of the coal, excluding information regarding mineral or elemental contents that are
potentially toxic in the environment, shall be kept confidential and not made a matter
of public record; (13) A detailed description of the measures to be taken during the mining and reclamation
process to ensure the protection of all of the following: (a) The quality of surface and ground water systems, both on- and off-site, from adverse
effects of the mining and reclamation process; (b) The rights of present users to such water; (c) The quantity of surface and ground water systems, both on- and off-site, from adverse
effects of the mining and reclamation process or, where such protection of quantity
cannot be assured, provision of alternative sources of water. (14) Any other requirements the chief prescribes by rule. (D)(1) Any information required by division (C) of this section that is not on public file
pursuant to this chapter shall be held in confidence by the chief. (2) With regard to requests for an exemption from the requirements of this chapter for
coal extraction incidental to the extraction of other minerals, as described in division (H)(1)(a) of section 1513.01 of the Revised Code , confidential information includes and is limited to information concerning trade
secrets or privileged commercial or financial information relating to the competitive
rights of the persons intending to conduct the extraction of minerals. (E)(1) Upon the basis of a complete mining application and reclamation plan or a revision
or renewal thereof, as required by this chapter, and information obtained as a result
of public notification and public hearing, if any, as provided by section 1513.071 of the Revised Code , the chief shall grant, require modification of, or deny the application for a permit
and notify the applicant in writing in accordance with division (I)(3) of this section. An application is deemed to be complete as submitted to the chief unless the chief,
within fourteen days of the submission, identifies deficiencies in the application
in writing and subsequently submits a copy of a written list of deficiencies to the
applicant. An application shall not be considered incomplete or denied by reason of right of
entry documentation, provided that the applicant documents the applicant's legal right
to enter and mine at least sixty-seven per cent of the total area for which coal mining
operations are proposed. A decision of the chief denying a permit shall state in writing the specific reasons
for the denial. The applicant for a permit or revision of a permit has the burden of establishing
that the application is in compliance with all the requirements of this chapter. Within ten days after the granting of a permit, the chief shall notify the boards
of township trustees and county commissioners, the mayor, and the legislative authority
in the township, county, and municipal corporation in which the area of land to be
affected is located that a permit has been issued and shall describe the location
of the land. However, failure of the chief to notify the local officials shall not affect the
status of the permit. (2) No permit application or application for revision of an existing permit shall be
approved unless the application affirmatively demonstrates and the chief finds in
writing on the basis of the information set forth in the application or from information
otherwise available, which shall be documented in the approval and made available
to the applicant, all of the following: (a) The application is accurate and complete and all the requirements of this chapter
have been complied with. (b) The applicant has demonstrated that the reclamation required by this chapter can
be accomplished under the reclamation plan contained in the application. (c)(i) Assessment of the probable cumulative impact of all anticipated mining in the general
and adjacent area on the hydrologic balance specified in division (B)(1)(k) of this
section has been made by the chief, and the proposed operation has been designed to
prevent material damage to hydrologic balance outside the permit area. (ii) There shall be an ongoing process conducted by the chief in cooperation with other
state and federal agencies to review all assessments of probable cumulative impact
of coal mining in light of post-mining data and any other hydrologic information as
it becomes available to determine if the assessments were realistic. The chief shall take appropriate action as indicated in the review process. (d) The area proposed to be mined is not included within an area designated unsuitable
for coal mining pursuant to section 1513.073 of the Revised Code or is not within an area under study for such designation in an administrative proceeding
commenced pursuant to division (A)(3)(c) or (B) of section 1513.073 of the Revised Code unless in an area as to which an administrative proceeding has commenced pursuant
to division (A)(3)(c) or (B) of section 1513.073 of the Revised Code , the operator making the permit application demonstrates that, prior to January 1,
1977, the operator made substantial legal and financial commitments in relation to
the operation for which a permit is sought. (e) In cases where the private mineral estate has been severed from the private surface
estate and surface disturbance will result from the applicant's proposed use of a
strip mining method, the applicant has submitted to the chief one of the following: (i) The written consent of the surface owner to the surface disturbance that will result
from the extraction of coal by the applicant's proposed strip mining method; (ii) A conveyance that expressly grants or reserves the right to extract the coal by strip
mining methods that cause surface disturbance; (iii) If the conveyance does not expressly grant the right to extract coal by strip mining
methods that cause surface disturbance, the surface-subsurface legal relationship
concerning surface disturbance shall be determined under the law of this state. This chapter does not authorize the chief to adjudicate property rights disputes. (3)(a) The applicant shall file with the permit application a schedule listing all notices
of violations of any law, rule, or regulation of the United States or of any department
or agency thereof or of any state pertaining to air or water environmental protection
incurred by the applicant in connection with any coal mining operation during the
three-year period prior to the date of application. The schedule also shall indicate the final resolution of such a notice of violation. Upon receipt of an application, the chief shall provide a schedule listing all notices
of violations of this chapter pertaining to air or water environmental protection
incurred by the applicant during the three-year period prior to receipt of the application
and the final resolution of all such notices of violation. The chief shall provide this schedule to the applicant for filing by the applicant
with the application filed for public review, as required by division (B)(5) of this
section. When the schedule or other information available to the chief indicates that any
coal mining operation owned or controlled by the applicant is currently in violation
of such laws, the permit shall not be issued until the applicant submits proof that
the violation has been corrected or is in the process of being corrected to the satisfaction
of the regulatory authority, department, or agency that has jurisdiction over the
violation and that any civil penalties owed to the state for a violation and not the
subject of an appeal have been paid. No permit shall be issued to an applicant after a finding by the chief that the
applicant or the operator specified in the application controls or has controlled
mining operations with a demonstrated pattern of willful violations of this chapter
of a nature and duration to result in irreparable damage to the environment as to
indicate an intent not to comply with or a disregard of this chapter. (b) For the purposes of division (E)(3)(a) of this section, any violation resulting from
an unanticipated event or condition at a surface coal mining operation on lands eligible
for remining under a permit held by the person submitting an application for a coal
mining permit under this section shall not prevent issuance of that permit. As used in this division, “ unanticipated event or condition ” means an event or condition encountered in a remining operation that was not contemplated
by the applicable surface coal mining and reclamation permit. (4)(a) In addition to finding the application in compliance with division (E)(2) of this
section, if the area proposed to be mined contains prime farmland as determined pursuant
to division (B)(1)(p) of this section, the chief, after consultation with the secretary
of the United States department of agriculture and pursuant to regulations issued
by the secretary of the interior with the concurrence of the secretary of agriculture,
may grant a permit to mine on prime farmland if the chief finds in writing that the
operator has the technological capability to restore the mined area, within a reasonable
time, to equivalent or higher levels of yield as nonmined prime farmland in the surrounding
area under equivalent levels of management and can meet the soil reconstruction standards
in section 1513.16 of the Revised Code . (b) Division (E)(4)(a) of this section does not apply to a permit issued prior to August
3, 1977, or revisions or renewals thereof. (5) The chief shall issue an order denying a permit after finding that the applicant
has misrepresented or omitted any material fact in the application for the permit. (6) The chief may issue an order denying a permit after finding that the applicant, any
partner, if the applicant is a partnership, any officer, principal shareholder, or
director, if the applicant is a corporation, or any other person who has a right to
control or in fact controls the management of the applicant or the selection of officers,
directors, or managers of the applicant has been a sole proprietor or partner, officer,
director, principal shareholder, or person having the right to control or has in fact
controlled the management of or the selection of officers, directors, or managers
of a business entity that ever has had a coal mining license or permit issued by this
or any other state or the United States suspended or revoked, ever has forfeited a
coal or surface mining bond, performance security, or similar security deposited in
lieu of bond in this or any other state or with the United States, or ever has substantially
or materially failed to comply with this chapter. (7) When issuing a permit under this section, the chief may authorize an applicant to
conduct coal mining and reclamation operations on areas to be covered by the permit
that were affected by coal mining operations before August 3, 1977, that have resulted
in continuing water pollution from or on the previously mined areas for the purpose
of potentially reducing the pollution loadings of pH, iron, and manganese from discharges
from or on the previously mined areas. Following the chief's authorization to conduct such operations on those areas, the
areas shall be designated as pollution abatement areas for the purposes of this chapter. The chief shall not grant an authorization under division (E)(7) of this section to
conduct coal mining and reclamation operations on any such previously mined areas
unless the applicant demonstrates to the chief's satisfaction that all of the following
conditions are met: (a) The applicant's pollution abatement plan for mining and reclaiming the previously
mined areas represents the best available technology economically achievable. (b) Implementation of the plan will potentially reduce pollutant loadings of pH, iron,
and manganese resulting from discharges of surface waters or ground water from or
on the previously mined areas within the permit area. (c) Implementation of the plan will not cause any additional degradation of surface water
quality off the permit area with respect to pH, iron, and manganese. (d) Implementation of the plan will not cause any additional degradation of ground water. (e) The plan meets the requirements governing mining and reclamation of such previously
mined pollution abatement areas established by the chief in rules adopted under section 1513.02 of the Revised Code . (f) Neither the applicant; any partner, if the applicant is a partnership; any officer,
principal shareholder, or director, if the applicant is a corporation; any other
person who has a right to control or in fact controls the management of the applicant
or the selection of officers, directors, or managers of the applicant; nor any contractor
or subcontractor of the applicant, has any of the following: (i) Responsibility or liability under this chapter or rules adopted under it as an operator
for treating the discharges of water pollutants from or on the previously mined areas
for which the authorization is sought; (ii) Any responsibility or liability under this chapter or rules adopted under it for
reclaiming the previously mined areas for which the authorization is sought; (iii) During the eighteen months prior to submitting the permit application requesting
an authorization under division (E)(7) of this section, had a coal mining and reclamation
permit suspended or revoked under division (D)(3) of section 1513.02 of the Revised Code for violating this chapter or Chapter 6111. of the Revised Code or rules adopted
under them with respect to water quality, effluent limitations, or surface or ground
water monitoring; (iv) Ever forfeited a coal or surface mining bond, performance security, or similar security
deposited in lieu of a bond in this or any other state or with the United States. (8) In the case of the issuance of a permit that involves a conflict of results between
various methods of calculating potential acidity and neutralization potential for
purposes of assessing the potential for acid mine drainage to occur at a mine site,
the permit shall include provisions for monitoring and record keeping to identify
the creation of unanticipated acid water at the mine site. If the monitoring detects the creation of acid water at the site, the permit shall
impose on the permittee additional requirements regarding mining practices and site
reclamation to prevent the discharge of acid mine drainage from the mine site. As used in division (E)(8) of this section, “potential acidity” and “neutralization
potential” have the same meanings as in section 1513.075 of the Revised Code . (F)(1) During the term of the permit, the permittee may submit an application for a revision
of the permit, together with a revised reclamation plan, to the chief. (2) An application for a revision of a permit shall not be approved unless the chief
finds that reclamation required by this chapter can be accomplished under the revised
reclamation plan. The revision shall be approved or disapproved within ninety days after receipt of
a complete revision application. The chief shall establish, by rule, criteria for determining the extent to which
all permit application information requirements and procedures, including notice and
hearings, shall apply to the revision request, except that any revisions that propose
significant alterations in the reclamation plan, at a minimum, shall be subject to
notice and hearing requirements. (3) Any extensions to the area covered by the permit except incidental boundary revisions
shall be made by application for a permit. (4) Documents or a notarized statement that form the basis of the applicant's legal right
to enter and commence coal mining operations on land that is located within an area
covered by the permit and that was legally acquired subsequent to the issuance of
the permit for the area shall be submitted with an application for a revision of the
permit. (G) No transfer, assignment, or sale of the rights granted under a permit issued pursuant
to this chapter shall be made without the written approval of the chief. (H) The chief, within a time limit prescribed in the chief's rules, shall review outstanding
permits and may require reasonable revision or modification of a permit. A revision or modification shall be based upon a written finding and subject to
notice and hearing requirements established by rule of the chief. (I)(1) If an informal conference has been held pursuant to section 1513.071 of the Revised Code , the chief shall issue and furnish the applicant for a permit, persons who participated
in the informal conference, and persons who filed written objections pursuant to division (B) of section 1513.071 of the Revised Code , with the written finding of the chief granting or denying the permit in whole or
in part and stating the reasons therefor within sixty days of the conference, provided
that the chief shall comply with the time frames established in division (I)(3) of
this section. (2) If there has been no informal conference held pursuant to section 1513.071 of the Revised Code , the chief shall submit to the applicant for a permit the written finding of the
chief granting or denying the permit in whole or in part and stating the reasons therefor
within the time frames established in division (I)(3) of this section. (3) The chief shall grant or deny a permit not later than two hundred forty days after
the submission of a complete application for the permit. Any time during which the applicant is making revisions to an application or providing
additional information requested by the chief regarding an application shall not be
included in the two hundred forty days. If the chief determines that a permit cannot be granted or denied within the two-hundred-forty-day
time frame, the chief, not later than two hundred ten days after the submission of
a complete application for the permit, shall provide the applicant with written notice
of the expected delay. (4) If the application is approved, the permit shall be issued. However, the permit shall prohibit the commencement of coal mining operations on
any land that is located within an area covered by the permit if the permittee has
not provided to the chief documents that form the basis of the permittee's legal right
to enter and conduct coal mining operations on that land. If the application is disapproved, specific reasons therefor shall be set forth
in the notification. Within thirty days after the applicant is notified of the final decision of the
chief on the permit application, the applicant or any person with an interest that
is or may be adversely affected may appeal the decision to the reclamation commission
pursuant to section 1513.13 of the Revised Code . (5) Any applicant or any person with an interest that is or may be adversely affected
who has participated in the administrative proceedings as an objector and is aggrieved
by the decision of the reclamation commission, or if the commission fails to act within
the time limits specified in this chapter, may appeal in accordance with section 1513.14 of the Revised Code .
Frequently Asked Questions About Ohio § 1513.07
What does Ohio Revised Code § 1513.07 cover?
Section 1513.07 is part of the Ohio Revised Code, the codified statutory law of Ohio. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Ohio § 1513.07?
A common citation format is "Ohio Revised Code § 1513.07" (Ohio). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Ohio law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Ohio official source linked on this page or consult a licensed Ohio attorney.
How does Ohio § 1513.07 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Ohio can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Ohio.