Ohio § 1506.07

Full text of Ohio Ohio Revised Code § 1506.07, with citation guidance and answers to common questions.

§ 1506.07.

(A) No later than December 31, 1994, the director of natural resources shall adopt, and

may subsequently amend or rescind, rules in accordance with Chapter 119. of the Revised

Code governing the erection, construction, and redevelopment of permanent structures

in Lake Erie coastal erosion areas identified under section 1506.06 of the Revised Code and such other rules as are necessary to implement this section.  The rules shall include, without limitation, a requirement that any person who intends

to erect, construct, or redevelop any permanent structure in a Lake Erie coastal erosion

area obtain a permit to do so from the director and requirements and procedures for

the issuance of such permits, including, without limitation, a requirement that no

later than thirty days after receiving a complete permit application, the director

either shall notify the applicant that the application is approved or denied and,

if denied, the reason for denial or shall notify the applicant of any modification

necessary to qualify the application for approval and a requirement that each permit

contain a reference to the volume and page of the deed record by which the current

owner of the property to be improved obtained title to it. The rules adopted under this division do not apply to the erection, construction,

or redevelopment of a permanent structure for which a permit was issued or plan was

approved by any state agency, political subdivision of this state, or federal agency

prior to any of the following: (1) The effective date of those rules; (2) The date the director notifies each municipal corporation, county, and township of

the final identification of the coastal erosion areas pursuant to section 1506.06 of the Revised Code ; (3) The date the director adopts the coastal management program document pursuant to section 1506.02 of the Revised Code . (B) No person shall erect, construct, or redevelop a permanent structure on land within

a Lake Erie coastal erosion area without a permit issued in accordance with rules

adopted under division (A) of this section.  The director shall grant a permit under those rules if the proposed site is protected

by an effective erosion control measure approved by the director that will protect

the permanent structure or if both of the following criteria are met: (1) The structure will be movable or will be situated as far landward as applicable zoning

resolutions or ordinances permit; (2) The person seeking the authorization will suffer exceptional hardship if the authorization

is not given. The approval of an effective erosion control measure by the director for the purposes

of this division does not create liability on the part of the director, the department

of natural resources, or the state, municipal corporation, county, or township regarding

the future protection of the site for which the measure was approved. The director shall not require a permit for the erection, construction, or redevelopment

of a permanent structure on any parcel of property within a Lake Erie coastal erosion

area if that property is not adjacent to Lake Erie. (C) The director or his authorized representative may issue a stop work order whenever

the director finds, after inspection, that any erection, construction, or redevelopment

is being conducted within a Lake Erie coastal erosion area in violation of division

(B) of this section. (D) A permit granted by the director under division (B) of this section is not required

within the territory of any county or municipal corporation that has adopted and is

enforcing a Lake Erie coastal erosion area resolution or ordinance within its zoning

or building regulations if the resolution or ordinance has been reviewed by the director

under this division and meets or exceeds the standards established under division

(B) of this section. No later than thirty days after adopting, amending, or rescinding a Lake Erie coastal

erosion area resolution or ordinance under this division, the legislative authority

of the county or municipal corporation shall submit it to the director for review

and comment.  No later than thirty days after receiving the resolution or ordinance, the director

shall notify the legislative authority that the resolution or ordinance does or does

not meet or exceed the standards established under division (B) of this section.  If it does, the director's notice also shall indicate that a permit granted by the

director under division (B) of this section is not required within the territory of

that county or municipal corporation.  If the resolution or ordinance does not meet those standards, the legislative authority

may submit a revised resolution or ordinance under this division until the director

notifies the legislative authority that the resolution or ordinance meets those standards. Beginning on the thirty-first day of January following the director's notice that

the resolution or ordinance meets or exceeds the standards established under division

(B) of this section, and every two years thereafter, the legislative authority shall

submit to the director, on a form created by the department, a report of the county's

or municipal corporation's relevant administrative and enforcement activities during

the previous two calendar years. If the director determines at any time that a Lake Erie coastal erosion area resolution

or ordinance that the director has determined under this division meets or exceeds

the standards established under division (B) of this section is being inadequately

enforced, the director shall so notify the legislative authority that adopted it and

also shall notify the legislative authority that it may respond to the director's

determination in accordance with the procedure for doing so established by rules adopted

under this section.  If after considering the legislative authority's response the director determines

that the resolution or ordinance still is being inadequately enforced, the director

shall reinstate the permit requirement of division (B) of this section within the

territory of the affected county or municipal corporation.

Frequently Asked Questions About Ohio § 1506.07

What does Ohio Revised Code § 1506.07 cover?

Section 1506.07 is part of the Ohio Revised Code, the codified statutory law of Ohio. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Ohio § 1506.07?

A common citation format is "Ohio Revised Code § 1506.07" (Ohio). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Ohio law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Ohio official source linked on this page or consult a licensed Ohio attorney.

How does Ohio § 1506.07 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Ohio can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Ohio.