§ 54-18-18. Contractor to be paid during progress of work - Retainage - Failure to pay Rate of interest - Investment of retainage

If the contractor to whom a contract for construction or the provision of equipment to the association is let properly performs the work therein designated, the mill manager, at least once in each calendar month during the continuance of the contract work, shall meet, receive, and consider estimates furnished by the agent, engineer, or architect acting for the association or if not so furnished, then by the contractor, and shall allow such estimates in an amount of the estimated value of the labor and material furnished upon the contract, and of the material then upon the ground for use in the contract, subject to retentions of ten percent of each estimate presented until the time the project is fifty percent completed, with no further retainage on estimates during the continuance of the contract. Notwithstanding the requirements of any other law, the industrial commission may authorize the mill manager to prepay for equipment prior to delivery to the construction site if the industrial commission determines: 1. Prepayment is in the best interest of the association; 2. The association's interest will be adequately protected; and 3. The equipment is of a type that is not fungible and could not be sold except at a discount to another because it is constructed to specifications required by the association. Upon completion of ninety-five percent of the contract according to the estimates, the association may pay to the contractor ninety-five percent of the amount retained from previous estimates. Any amount retained after ninety-five percent completion of the contract must be paid to the contractor in such amounts and at such times as are approved by the association, upon estimates by its agent, engineer, or architect or the contractor, with final payment of all moneys due to the contractor to be made immediately following completion and acceptance of the project. Immediately after considering and allowing any such estimate, the association shall certify and promptly draw a warrant upon the proper fund and transmit it to the contractor entitled to it. If the association fails or neglects to receive and allow the estimate or certify any estimate or final payment upon completion and acceptance for a period of more than thirty days from the date of the estimate or completion date, then the estimate or final payment, with any retainage properly payable, shall draw interest from its date at the rate per annum of two percentage points below the Bank of North Dakota prime interest rate as set thirty days from the date of the estimate or completion date until the issuance of a proper warrant therefor. Such interest must be computed and added to the face of the estimate, final payment, or retainage by the officer required to issue the warrant, must be included in the warrant when drawn, and must be charged to the fund from which payment for the improvement is to be made. On the amounts of estimates retained, as provided herein, the association may invest or deposit the retained amounts in the Bank of North Dakota earning interest or dividends for the benefit of the contractor. Any amount so invested or deposited must remain in the name of the association until final payment of all moneys due to the contractor is to be made. Further, no contractor shall use such account in any manner whatsoever until released and received by the contractor upon completion of the contract.

Source: official North Dakota text · Last verified 2026-08-27

Frequently Asked Questions About North Dakota § 54-18-18

What does North Dakota Century Code § 54-18-18 cover?

Section 54-18-18 ("Contractor to be paid during progress of work - Retainage - Failure to pay Rate of interest - Investment of retainage") is part of the North Dakota Century Code, the codified statutory law of North Dakota. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite North Dakota § 54-18-18?

A common citation format is "North Dakota Century Code § 54-18-18" (North Dakota). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of North Dakota law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the North Dakota official source linked on this page or consult a licensed North Dakota attorney.

How does North Dakota § 54-18-18 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in North Dakota can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in North Dakota.