North Carolina § 62-156 - Power sales by small power producers to public utilities.
Full text of North Carolina North Carolina General Statutes § 62-156 — Power sales by small power producers to public utilities., with citation guidance and answers to common questions.
§ 62-156. Power sales by small power producers to public utilities.
In the event that a small power producer and an electric public utility are unable to mutually agree to a contract for the sale of electricity or to a price for the electricity purchased by the electric public utility, the Commission shall require the electric public utility to purchase the power, under rates and terms established as provided in subsection (b) or (c) of this section. At least every two years, the Commission shall determine the standard contract avoided cost rates to be included within the tariffs of each electric public utility and paid by electric public utilities for power purchased from small power producers, according to the following standards: Standard Contract for Small Power Producers up to 1,000 kilowatts (kW). - The Commission shall approve a standard offer power purchase agreement to be used by the electric public utility in purchasing energy and capacity from small power producers subject to this subsection. Long-term contracts up to 10 years for the purchase of electricity by the electric public utility from small power producers with a design capacity up to and including 1,000 kilowatts (kW) shall be encouraged in order to enhance the economic feasibility of these small power production facilities; provided, however, that when an electric public utility, pursuant to this subsection, has entered into power purchase agreements with small power producers from facilities (i) in the aggregate capacity of 100 megawatts (MW) or more and (ii) which established a legally enforceable obligation after November 15, 2016, the eligibility threshold for that utility's standard offer shall be reduced to 100 kilowatts (kW). Avoided Cost of Energy to the Utility. - The rates paid by an electric public utility to a small power producer for energy shall not exceed, over the term of the purchase power contract, the incremental cost to the electric public utility of the electric energy which, but for the purchase from a small power producer, the utility would generate or purchase from another source. A determination of the avoided energy costs to the utility shall include a consideration of the following factors over the term of the power contracts: the expected costs of the additional or existing generating capacity which could be displaced, the expected cost of fuel and other operating expenses of electric energy production which a utility would otherwise incur in generating or purchasing power from another source, and the expected security of the supply of fuel for the utilities' alternative power sources. Availability and Reliability of Power. - The rates to be paid by electric public utilities for capacity purchased from a small power producer shall be established with consideration of the reliability and availability of the power. A future capacity need shall only be avoided in a year where the utility's most recent biennial integrated resource plan filed with the Commission pursuant to G.S. 62-110.1(c) has identified a projected capacity need to serve system load and the identified need can be met by the type of small power producer resource based upon its availability and reliability of power, other than for (i) swine or poultry waste for which a need is established consistent with G.S. 62-133.8(e) and (f) and (ii) hydropower small power producers with power purchase agreements with an electric public utility in effect as of July 27, 2017, and the renewal of such a power purchase agreement, if the hydroelectric small power producer's facility total capacity is equal to or less than five megawatts (MW). Rates to be paid by electric public utilities to small power producers not eligible for the utility's standard contract pursuant to subsection (b) of this section shall be established through good-faith negotiations between the utility and small power producer, subject to the Commission's oversight as required by law. In establishing rates for purchases from such small power producers, the utility shall design rates consistent with the most recent Commission-approved avoided cost methodology for a fixed five-year term. Rates for such purchases shall take into account factors related to the individual characteristics of the small power producer, as well as the factors identified in subdivisions (2) and (3) of subsection (b) of this section. Notwithstanding this subsection, small power producers that produce electric energy primarily by the use of any of the following renewable energy resources may negotiate for a fixed-term contract that exceeds five years: (i) swine or poultry waste; (ii) hydropower, if the hydroelectric power facility total capacity is equal to or less than five megawatts (MW); or (iii) landfill gas, manure digester gas, agricultural waste digester gas, sewage digester gas, or sewer sludge digester gas. Notwithstanding any other provision of this section, an electric public utility shall not be required to enter into a contract with or purchase power from a small power producer if the electric public utility's obligation to purchase from such small power producers has been terminated pursuant to 18 C.F.R. § 292.309. History (1979, 2nd Sess., c. 1219, s. 2; 2017-192, s. 1(b); 2019-132, s. 3(a).) Editor's Note. - Session Laws 2017-192, s. 1(c), provides: "A small power production facility which would otherwise be eligible for the standard offer rate schedules and power purchase agreement terms and conditions approved by the Commission in Docket No. E-100, Sub 140, but which fails to commence delivering power to the utility on or before September 10, 2018, shall, notwithstanding such failure, remain eligible for such rate schedules and terms and conditions, unless the nameplate capacity of the generation facility when taken together with the nameplate capacity of other generation facilities connected to the same substation transformer exceeds the nameplate capacity of the substation transformer. The term of a power purchase agreement eligible for such rate schedules and terms and conditions pursuant to this section shall commence on September 10, 2018, and shall end on the date that is 15 years after the commencement date. An electric public utility shall have the option in its discretion of electing not to interconnect to its distribution system a solar photovoltaic facility with a nameplate capacity of 10 megawatts (MW) or greater that had not executed an interconnection agreement prior to July 1, 2017, and instead requiring such facility to interconnect to the utility's transmission system." Session Laws 2017-192, s. 1(d), provides: "This section is effective when it becomes law [July 27, 2017]. Subsection (b) of this section applies to any standard contract rates and terms approved by the Commission or nonstandard negotiated agreements entered into between a small power producer and the electric public utility on or after that date. Subsection (c) of this section applies to small power production facilities that established a legally enforceable obligation in accordance with the Commission's then applicable requirements on or before November 15, 2016." Session Laws 2017-192, s. 14(a), contains a severability clause. Session Laws 2019-132, s. 3(b), provides: "The exception for hydropower small power producers from limitations on capacity payments established in G.S. 62-156(b)(3), as amended by Section 3(a) of this act, shall not be construed in any manner to affect the applicability of G.S. 62-156(b)(3) as it relates to any other small power producer." Effect of Amendments. - Session Laws 2017-192, s. 1(b), rewrote the section. For effective date and applicability, see editor's note. Session Laws 2019-132, s. 3(a), effective July 19, 2019, inserted "for (i)" and added "and (ii) hydropower small power producers with power purchase agreements with an electric public utility in effect as of July 27, 2017, and the renewal of such a power purchase agreement, if the hydroelectric small power producer's facility total capacity is equal to or less than five megawatts (MW)" in subdivision (b)(3).
Source: official North Carolina text · Last verified 2026-08-27
Frequently Asked Questions About North Carolina § 62-156
What does North Carolina General Statutes § 62-156 cover?
Section 62-156 ("Power sales by small power producers to public utilities.") is part of the North Carolina General Statutes, the codified statutory law of North Carolina. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite North Carolina § 62-156?
A common citation format is "North Carolina General Statutes § 62-156" (North Carolina). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of North Carolina law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the North Carolina official source linked on this page or consult a licensed North Carolina attorney.
How does North Carolina § 62-156 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in North Carolina can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in North Carolina.