§ 143-128. 1. Construction management at risk contracts.

For purposes of this section and G.S. 143-64.31: "Construction management services" means services provided by a construction manager, which may include preparation and coordination of bid packages, scheduling, cost control, value engineering, evaluation, preconstruction services, and construction administration. "Construction management at risk services" means services provided by a person, corporation, or entity that (i) provides construction management services for a project throughout the preconstruction and construction phases, (ii) who is licensed as a general contractor, and (iii) who guarantees the cost of the project. "Construction manager at risk" means a person, corporation, or entity that provides construction management at risk services. "First-tier subcontractor" means a subcontractor who contracts directly with the construction manager at risk. The construction manager at risk shall be selected in accordance with Article 3D of this Chapter. Design services for a project shall be performed by a licensed architect or engineer. The public owner shall contract directly with the architect or engineer. The public owner shall make a good-faith effort to comply with G.S. 143-128.2, G.S. 143-128.4, and to recruit and select small business entities when selecting a construction manager at risk. The construction manager at risk shall contract directly with the public entity for all construction; shall publicly advertise as prescribed in G.S. 143-129; and shall prequalify and accept bids from first-tier subcontractors for all construction work under this section. The construction manager at risk shall use the prequalification process determined by the public entity in accordance with G.S. 143-135.8, provided that public entity and the construction manager at risk shall jointly develop the assessment tool and criteria for that specific project, which must include the prequalification scoring values and minimum required score for prequalification on that project. The public entity shall require the construction manager at risk to submit its plan for compliance with G.S. 143-128.2 for approval by the public entity prior to soliciting bids for the project's first-tier subcontractors. A construction manager at risk and first-tier subcontractors shall make a good faith effort to comply with G.S. 143-128.2, G.S. 143-128.4, and to recruit and select small business entities. A construction manager at risk may perform a portion of the work only if (i) bidding produces no responsible, responsive bidder for that portion of the work, the lowest responsible, responsive bidder will not execute a contract for the bid portion of the work, or the subcontractor defaults and a prequalified replacement cannot be obtained in a timely manner, and (ii) the public entity approves of the construction manager at risk's performance of the work. All bids shall be opened publicly, and once they are opened, shall be public records under Chapter 132 of the General Statutes. The construction manager at risk shall act as the fiduciary of the public entity in handling and opening bids. The construction manager at risk shall award the contract to the lowest responsible, responsive bidder, taking into consideration quality, performance, the time specified in the bids for performance of the contract, the cost of construction oversight, time for completion, compliance with G.S. 143-128.2, and other factors deemed appropriate by the public entity and advertised as part of the bid solicitation. The public entity may require the selection of a different first-tier subcontractor for any portion of the work, consistent with this section, provided that the construction manager at risk is compensated for any additional cost incurred. The construction manager at risk shall provide a performance and payment bond to the public entity in accordance with the provisions of Article 3 of Chapter 44A of the General Statutes. Construction management at risk services may be used by the public entity only after the public entity has concluded that construction management at risk services is in the best interest of the project, and the public entity has compared the advantages and disadvantages of using the construction management at risk method for a given project in lieu of the delivery methods identified in G.S. 143-128(a1)(1) through G.S. 143-128(a1)(3). The public entity may not delegate this determination. When contracts are awarded pursuant to this section, the public entity shall provide for a dispute resolution procedure as provided in G.S. 143-128(f1) . History (2001-496, s. 2; 2013-401, s. 5; 2014-42, s. 2.) Editor's Note. - Session Laws 2013-401, provides in its preamble: "Whereas, the legislature recognizes that there is a public need for the design, construction, improvement, renovation, and expansion of high-performing public buildings within the State of North Carolina; and "Whereas, the public need may not be, in limited situations, wholly satisfied by existing procurement methods in which public buildings are designed, constructed, improved, renovated, or expanded; and "Whereas, many local governmental entities request special legislative authorization to enter into public-private partnerships and use design-build contracting every legislative session; and "Whereas, in some instances, more efficient delivery of quality design and construction can be realized when a governmental entity is authorized to utilize an integrated approach for the design and construction of a project under one contract with a single point of responsibility; and "Whereas, the design-build integrated approach to project delivery, based upon qualifications and experience, in some instances, can yield improved collaboration among design professionals, builders, and owners throughout the entire process and deliver a quality and cost-efficient building; and "Whereas, certain governmental entities within the State lack the financial resources required to undertake capital building construction projects that are necessary to satisfy critical public needs; and "Whereas, partnerships with private developers may offer an effective financial mechanism for governmental entities to secure public buildings to satisfy critical public needs that cannot otherwise be met; and "Whereas, the legislature recognizes that the general public must have confidence in governmental entities' processes for construction contracting; and "Whereas, the legislature realizes that open competition delivers the best value for taxpayers and public owners; and "Whereas, the legislature seeks to create transparent, fair, and equitable contracting procedures for the use of public funds in government construction contracting; and "Whereas, the legislation proposed in this act is not intended to affect the existing statutes, regulations, or practices relevant to projects administered by the North Carolina Department of Transportation nor licensing requirements of designers or contractors; Now, therefore," Session Laws 2014-42, s. 10, made the amendment to this section by Session Laws 2014-42, s. 2, applicable to contracts awarded on or after October 1, 2014. Effect of Amendments. - Session Laws 2013-401, s. 5, added the last sentence in subsection (b); and substituted "to comply with G.S. 143-128.2 , G.S. 143-128.4 , and to recruit and select small business entities" for "to recruit and select minority businesses for participation in contracts pursuant to G.S. 143-128.2 " in the fourth sentence of subsection (c). For effective date and applicability, see Editor's note. Session Laws 2014-42, s. 2, effective October 1, 2014, in the second sentence of subsection (c), substituted "construction manager at risk shall use the prequalification process determined by the public entity in accordance with G.S. 143-135.8 , provided that public entity and the construction manager at risk shall jointly develop the assessment tool and criteria for that specific project, which must include the prequalification scoring values and minimum required score for prequalification on that project" for "prequalification criteria shall be determined by the public entity and the construction manager at risk to address quality, performance, the time specified in the bids for performance of the contract, the cost of construction oversight, time for completion, capacity to perform, and other factors deemed appropriate by the public entity" and added subsection (e). See Editor's note for applicability.

Source: official North Carolina text · Last verified 2026-08-27

Frequently Asked Questions About North Carolina § 143-128

What does North Carolina General Statutes § 143-128 cover?

Section 143-128 ("1. Construction management at risk contracts.") is part of the North Carolina General Statutes, the codified statutory law of North Carolina. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite North Carolina § 143-128?

A common citation format is "North Carolina General Statutes § 143-128" (North Carolina). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of North Carolina law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the North Carolina official source linked on this page or consult a licensed North Carolina attorney.

How does North Carolina § 143-128 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in North Carolina can advise on how this section applies to you. Contact your state or local bar association for a referral.