New Jersey § 40a:11-16
Full text of New Jersey New Jersey Statutes § 40a:11-16, with citation guidance and answers to common questions.
§ 40a:11-16.
All construction contracts issued by a contracting unit for bids which were advertised
on or after the effective date of P.L.2017, c. 317 ( C.40A:11-16.7 et seq. ) shall include the changed conditions contract provisions set forth in this section,
which provisions shall be deemed to be a part of any such contract even if not expressly
incorporated therein, and which provisions may not be modified in any manner by the
contracting unit. a. A contract subject to this section shall include the following differing site conditions
provisions: (1) If the contractor encounters differing site conditions during the progress of
the work of the contract, the contractor shall promptly notify the contracting unit
in writing of the specific differing site conditions encountered before the site is
further disturbed and before any additional work is performed in the impacted area. (2) Upon receipt of a differing site conditions notice in accordance with paragraph
(1) of this subsection, or upon the contracting unit otherwise learning of differing
site conditions, the contracting unit shall promptly undertake an investigation to
determine whether differing site conditions are present. (3) If the contracting unit determines different site conditions that may result in
additional costs or delays exist, the contracting unit shall provide prompt written
notice to the contractor containing directions on how to proceed. (4)(a) The contracting unit shall make a fair and equitable adjustment to the contract
price and contract completion date for increased costs and delays resulting from the
agreed upon differing site conditions encountered by the contractor. (b) If both parties agree that the contracting unit's investigation and directions
decrease the contractor's costs or time of performance, the contracting unit shall
be entitled to a fair and equitable downward adjustment of the contract price or time
of performance. (c) If the contracting unit determines that there are no differing site conditions
present that would result in additional costs or delays, the contracting unit shall
so advise the contractor, in writing, and the contractor shall resume performance
of the contract, and shall be entitled to pursue a differing site conditions claim
against the contracting unit for additional compensation or time attributable to the
alleged differing site conditions. (5) Execution of the contract by the contractor shall constitute a representation
that the contractor has visited the site and has become generally familiar with the
local conditions under which the work is to be performed. (6) As used in this subsection, “ differing site conditions ” mean physical conditions at the contract work site that are subsurface or otherwise
concealed and which differ materially from those indicated in the contract documents
or are of such an unusual nature that the conditions differ materially from those
ordinarily encountered and generally recognized as inherent in the work of the character
provided for in the contract. b. A contract subject to this section shall include the following suspension of work
provisions: (1) The contracting unit shall provide written notice to the contractor in advance
of any suspension of work lasting more than 10 calendar days of the performance of
all or any portion of the work of the contract. (2) If the performance of all or any portion of the work of the contract is suspended
by the contracting unit for more than 10 calendar days due to no fault of the contractor
or as a consequence of an occurrence beyond the contracting unit's control, the contractor
shall be entitled to compensation for any resultant delay to the project completion
or additional contractor expenses, and to an extension of time, provided that, to
the extent feasible, the contractor, within 10 calendar days following the conclusion
of the suspension, notifies the contracting unit, in writing, of the nature and extent
of the suspension of work. The notice shall include available supporting information, which information may
thereafter be supplemented by the contractor as needed and as may be reasonably requested
by the contracting unit. Whenever a work suspension exceeds 60 days, upon seven days' written notice, either
party shall have the option to terminate the contract for cause and to be fairly and
equitably compensated therefor. (3) Upon receipt of the contractor's suspension of work notice in accordance with
paragraph (2) of this subsection, the contracting unit shall promptly evaluate the
contractor's notice and promptly advise the contractor of its determination on how
to proceed in writing. (4)(a) If the contracting unit determines that the contractor is entitled to additional
compensation or time, the contracting unit shall make a fair and equitable upward
adjustment to the contract price and contract completion date. (b) If the contracting unit determines that the contractor is not entitled to additional
compensation or time, the contractor shall proceed with the performance of the contract
work, and shall be entitled to pursue a suspension of work claim against the contracting
unit for additional compensation or time attributable to the suspension. (5) Failure of the contractor to provide timely notice of a suspension of work shall
result in a waiver of a claim if the contracting unit can prove by clear and convincing
evidence that the lack of notice or delayed notice by the contractor actually prejudiced
the contracting unit's ability to adequately investigate and defend against the claim. c. A contract subject to this section shall include the following change in character
of work provisions: (1) If the contractor believes that a change directive by the contracting unit results
in a material change to the contract work, the contractor shall so notify the contracting
unit in writing. The contractor shall continue to perform all work on the project that is not the
subject of the notice. (2) Upon receipt of the contractor's change in character notice in accordance with
paragraph (1) of this subsection, the contracting unit shall promptly evaluate the
contractor's notice and promptly advise the contractor of its determination on how
to proceed in writing. (3)(a) If the contracting unit determines that a change to the contractor's work caused
or directed by the contracting unit materially changes the character of any aspect
of the contract work, the contracting unit shall make a fair and equitable upward
adjustment to the contract price and contract completion date. The basis for any such price adjustment shall be the difference between the cost
of performance of the work as planned at the time of contracting and the actual cost
of such work as a result of its change in character, or as otherwise mutually agreed
upon by the contractor and the contracting unit prior to the contractor performing
the subject work. (b) If the contracting unit determines that the contractor is not entitled to additional
compensation or time, the contractor shall continue the performance of all contract
work, and shall be entitled to pursue a claim against the contracting unit for additional
compensation or time attributable to the alleged material change. (4) As used in this subsection, “ material change ” means a character change which increases or decreases the contractor's cost of performing
the work, increases or decreases the amount of time by which the contractor completes
the work in relation to the contractually required completion date, or both. d. A contract subject to this section shall include the following change in quantity
provisions: (1) The contracting unit may increase or decrease the quantity of work to be performed
by the contractor. (2)(a) If the quantity of a pay item is cumulatively increased or decreased by 20
percent or less from the bid proposal quantity, the quantity change shall be considered
a minor change in quantity. (b) If the quantity of a pay item is increased or decreased by more than 20 percent
from the bid proposal quantity, the quantity change shall be considered a major change
in quantity. (3) For any minor change in quantity, the contracting unit shall make payment for
the quantity of the pay item performed at the bid price for the pay item. (4)(a) For a major increase in quantity, the contracting unit or contractor may request
to renegotiate the price for the quantity in excess of 120 percent of the bid proposal
quantity. If a mutual agreement cannot be reached on a negotiated price for a major quantity
increase, the contracting unit shall pay the actual costs plus an additional 10 percent
for overhead and an additional 10 percent for profit, unless otherwise specified in
the original bid. (b) For a major decrease in quantity, the contracting unit or contractor may request
to renegotiate the price for the quantity of work performed. If a mutual agreement cannot be reached on a negotiated price for a major quantity
decrease, the contracting unit shall pay the actual costs plus an additional 10 percent
for overhead and an additional 10 percent for profit, unless otherwise specified in
the original bid; provided, however, that the contracting unit shall not make a payment
in an amount that exceeds 80 percent of the value of the bid price multiplied by the
bid proposal quantity. (5) As used in this subsection, the term “ bid proposal quantity ” means the quantity indicated in the bid proposal less the quantities designated
in the project plans as “if and where directed.”
Frequently Asked Questions About New Jersey § 40a:11-16
What does New Jersey Statutes § 40a:11-16 cover?
Section 40a:11-16 is part of the New Jersey Statutes, the codified statutory law of New Jersey. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite New Jersey § 40a:11-16?
A common citation format is "New Jersey Statutes § 40a:11-16" (New Jersey). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of New Jersey law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the New Jersey official source linked on this page or consult a licensed New Jersey attorney.
How does New Jersey § 40a:11-16 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in New Jersey can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in New Jersey.