Nevada § 624.626 - Grounds and procedure for stopping work or terminating agreement; change orders; damages and other remedies; rights of lower-tiered subcontractors after work stoppage or termination of agreement; limitations on liability
Full text of Nevada Nevada Revised Statutes § 624.626 — Grounds and procedure for stopping work or terminating agreement; change orders; damages and other remedies; rights of lower-tiered subcontractors after work stoppage or termination of agreement; limitations on liability, with citation guidance and answers to common questions.
§ 624.626. Grounds and procedure for stopping work or terminating agreement; change orders; damages and other remedies; rights of lower-tiered subcontractors after work stoppage or termination of agreement; limitations on liability
1. If: (a) A higher-tiered contractor fails to pay the lower-tiered subcontractor within
the time provided in subsection 1 or 4 of NRS 624.624 ; (b) A higher-tiered contractor fails to pay the lower-tiered subcontractor within
45 days after the 25th day of the month in which the lower-tiered subcontractor submits
a request for payment, even if the higher-tiered contractor has not been paid and
the agreement contains a provision which requires the higher-tiered contractor to
pay the lower-tiered subcontractor only if or when the higher-tiered contractor is
paid; (c) A higher-tiered contractor fails to give the lower-tiered subcontractor written
notice of any withholding in the time and manner required by subsection 3 or 4 of NRS 624.624 ; (d) After receipt of a notice of withholding pursuant to subsection 3 or 4 of NRS 624.624 , the lower-tiered subcontractor gives the higher-tiered contractor written notice
pursuant to subsection 4 of NRS 624.624 and thereby disputes in good faith and for reasonable cause the amount withheld or
the condition or reason for the withholding; or (e) Within 30 days after the date that a written request for a change order is submitted
by the lower-tiered subcontractor to the higher-tiered contractor, the higher-tiered
contractor fails to: (1) Issue the change order; or (2) If the request for a change order is unreasonable, give written notice to the
lower-tiered subcontractor of the reasons why the change order is unreasonable, the lower-tiered subcontractor may stop work under the agreement until payment is
received if the lower-tiered subcontractor gives written notice to the higher-tiered
contractor at least 10 days before stopping work. 2. If a lower-tiered subcontractor stops work pursuant to paragraph (a), (c) or (d)
of subsection 1, the lower-tiered subcontractor may terminate the agreement with the
higher-tiered contractor by giving written notice of the termination to the higher-tiered
contractor after stopping work but at least 15 days before the termination of the
agreement. If the lower-tiered subcontractor is paid the amount due before the date for termination
set forth in the written notice, the lower-tiered subcontractor shall not terminate
the agreement and shall resume work. 3. If a higher-tiered contractor fails to issue a change order or fails to give written
notice pursuant to paragraph (e) of subsection 1: (a) The agreement price must be increased by the amount sought in the request for
a change order; (b) The time for performance must be extended by the amount sought in the request
for a change order; (c) The lower-tiered subcontractor may submit to the higher-tiered contractor a bill
or invoice for the labor, materials, equipment or services that are the subject of
the request for a change order; and (d) The higher-tiered contractor shall pay the lower-tiered subcontractor for such
labor, materials, equipment or services with the next payment made to the lower-tiered
subcontractor. 4. If an owner or higher-tiered contractor through his or her own act or neglect,
or through an act or neglect of his or her agent, excluding acts of God, floods, fires,
labor disputes, strikes or reasonable adjustments in work schedules, causes the work
to be stopped for a period of 15 days or more, the lower-tiered subcontractor may
terminate the agreement if: (a) The lower-tiered subcontractor gives written notice of his or her intent to terminate
to the higher-tiered contractor at least 10 days before terminating the agreement;
and (b) The higher-tiered contractor fails to allow the lower-tiered subcontractor to
resume the work within the time set forth in the written notice given pursuant to
paragraph (a). 5. If a lower-tiered subcontractor stops work pursuant to paragraph (a), (c) or (d)
of subsection 1, the higher-tiered contractor may terminate the agreement by giving
the lower-tiered subcontractor written notice of his or her intent to terminate at
least 15 days before terminating the agreement. 6. If the agreement is terminated pursuant to subsection 4, or if the lower-tiered
subcontractor stops work in accordance with this section and the agreement is terminated
pursuant to subsection 2 or 5, the lower-tiered subcontractor is entitled to recover
from the higher-tiered contractor with whom the lower-tiered subcontractor has entered
into an agreement the amount found by a trier of fact to be due the lower-tiered subcontractor,
including, without limitation: (a) The cost of all work, labor, materials, equipment and services furnished by and
through the lower-tiered subcontractor, including any overhead the lower-tiered subcontractor
and his or her lower-tiered subcontractors and suppliers incurred and profit the lower-tiered
subcontractor and his or her lower-tiered subcontractors and suppliers earned through
the date of termination; (b) The balance of the profit that the lower-tiered subcontractor and his or her lower-tiered
subcontractors and suppliers would have received if the agreement had been performed
in full; (c) Interest determined pursuant to NRS 624.630 ; and (d) The reasonable costs, including court costs and arbitration costs, incurred by
the lower-tiered subcontractor and his or her lower-tiered subcontractors in collecting
the amount due. In any action brought to enforce the rights or obligations set forth in this subsection,
the trier of fact may award reasonable attorney's fees to the lower-tiered subcontractor
and his or her lower-tiered subcontractors and suppliers or, if the trier of fact
determines that the lower-tiered subcontractor stopped work or terminated the agreement
without a reasonable basis in law or fact, the trier of fact may award reasonable
attorney's fees and costs, including court costs and arbitration costs, to the higher-tiered
contractor. 7. If a lower-tiered subcontractor stops work pursuant to this section, each lower-tiered
subcontractor with whom the lower-tiered subcontractor has entered into an agreement
and who has not fully performed under the agreement may also stop work on the work
of improvement. If a lower-tiered subcontractor terminates an agreement pursuant to this section,
all of his or her lower-tiered subcontractors may terminate their agreements with
the lower-tiered subcontractor. 8. The right of a lower-tiered subcontractor to stop work or terminate an agreement
pursuant to this section is in addition to all other rights that the lower-tiered
subcontractor may have at law or in equity and does not impair or affect the right
of a lower-tiered subcontractor to maintain a civil action or to submit any controversy
arising under the agreement to arbitration. 9. No lower-tiered subcontractor or his or her lower-tiered subcontractors or suppliers,
or their respective sureties, may be held liable for any delays or damages that an
owner or higher-tiered contractor may suffer as a result of the lower-tiered subcontractor
and his or her lower-tiered subcontractors and suppliers stopping their work or the
provision of materials or equipment or terminating an agreement for a reasonable basis
in law or fact and in accordance with this section.
Source: official Nevada text · Last verified 2026-08-27
Frequently Asked Questions About Nevada § 624.626
What does Nevada Revised Statutes § 624.626 cover?
Section 624.626 ("Grounds and procedure for stopping work or terminating agreement; change orders; damages and other remedies; rights of lower-tiered subcontractors after work stoppage or termination of agreement; limitations on liability") is part of the Nevada Revised Statutes, the codified statutory law of Nevada. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Nevada § 624.626?
A common citation format is "Nevada Revised Statutes § 624.626" (Nevada). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Nevada law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Nevada official source linked on this page or consult a licensed Nevada attorney.
How does Nevada § 624.626 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Nevada can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Nevada.