Nevada § 338.635 - Action by subcontractor or supplier to remedy unjustified or excessive withholding
Full text of Nevada Nevada Revised Statutes § 338.635 — Action by subcontractor or supplier to remedy unjustified or excessive withholding, with citation guidance and answers to common questions.
§ 338.635. Action by subcontractor or supplier to remedy unjustified or excessive withholding
1. A subcontractor or supplier who believes that the amount withheld by the contractor
or subcontractor is not justified or is excessive may apply to the district court
of the county where the public work or a part thereof is located for an order directing
the contractor or subcontractor to appear before the court to show cause why the relief
requested should not be granted. 2. The motion must: (a) Set forth the grounds upon which relief is requested; and (b) Be accompanied by a notarized affidavit signed by the petitioner or his or her
attorney that sets forth the facts upon which the motion is based. 3. If the court orders a hearing based upon the motion, the petitioner shall serve
the notice of the motion and the order of the court on the respondent within 3 days
after the court issues the order. The court shall conduct the hearing not less than 10 days and not more than 20 days
after the court issues the order for a hearing. 4. The order for a hearing must include a statement that, if the respondent fails
to appear at the time and place of the hearing, the court will order the respondent
to pay to the petitioner: (a) The entire amount that was withheld by the respondent, or a portion thereof; (b) Interest on the amount that was withheld by the respondent, or a portion thereof; (c) The costs incurred by the petitioner, including, without limitation, his or her
attorney's fees; or (d) Any combination of paragraphs (a), (b) and (c). 5. If, when the motion is filed, there is a civil action pending between the petitioner
and the respondent, the motion must be consolidated into the civil action. 6. If the court determines that: (a) The amount withheld is not justified, the court shall order the respondent to
pay to the petitioner the amount that was withheld. (b) The amount withheld is excessive, the court shall order the respondent to pay
to the petitioner an amount determined by the court. (c) The amount withheld is justified, the court shall issue an order approving the
amount that was withheld by the respondent. 7. The proceedings conducted pursuant to the provisions of this section do not affect
any other rights or remedies provided by law or contract.
Source: official Nevada text · Last verified 2026-08-27
Frequently Asked Questions About Nevada § 338.635
What does Nevada Revised Statutes § 338.635 cover?
Section 338.635 ("Action by subcontractor or supplier to remedy unjustified or excessive withholding") is part of the Nevada Revised Statutes, the codified statutory law of Nevada. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Nevada § 338.635?
A common citation format is "Nevada Revised Statutes § 338.635" (Nevada). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Nevada law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Nevada official source linked on this page or consult a licensed Nevada attorney.
How does Nevada § 338.635 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Nevada can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Nevada.