Nebraska § 73-1115 - Construction managers; submission of proposals; ranking; negotiation of contract.
Full text of Nebraska Revised Statutes of Nebraska § 73-1115 — Construction managers; submission of proposals; ranking; negotiation of contract., with citation guidance and answers to common questions.
§ 73-1115. Construction managers; submission of proposals; ranking; negotiation of contract.
(1) Construction managers shall submit proposals as required by the request for proposals.
(2) A proposal may be submitted in paper or electronic format. All proposals shall be sealed and shall not be opened until expiration of the time established for making the proposals as set forth in the request for proposals.
(3) Proposals may be withdrawn at any time prior to signing a contract for preconstruction services. The authorized agency shall have the right to reject any and all proposals at no cost to the authorized agency. The authorized agency may thereafter solicit new proposals or may cancel the construction manager-general contractor procurement process.
(4) The authorized agency shall rank the construction managers in accordance with the qualification-based selection process and pursuant to the criteria in the request for proposals. The authorized agency may meet with construction managers prior to the ranking.
(5) The authorized agency may attempt to negotiate a contract for preconstruction services with the highest ranked construction manager and may enter into a contract for preconstruction services after negotiations. If the authorized agency is unable to negotiate a satisfactory contract for preconstruction services with the highest ranked construction manager, the authorized agency may terminate negotiations with that construction manager. The authorized agency may then undertake negotiations with the second highest ranked construction manager and may enter into a contract for preconstruction services after negotiations. If the authorized agency is unable to negotiate a satisfactory contract with the second highest ranked construction manager, the authorized agency may undertake negotiations with the third highest ranked construction manager, if any, and may enter into a contract for preconstruction services after negotiations.
(6) If the authorized agency is unable to negotiate a satisfactory contract for preconstruction services with any of the ranked construction managers, the authorized agency may either revise the request for proposals and solicit new proposals or cancel the construction manager-general contractor contract process under the State Building Construction Alternatives Act.
Source: official Nebraska text · Last verified 2026-08-27
Frequently Asked Questions About Nebraska § 73-1115
What does Revised Statutes of Nebraska § 73-1115 cover?
Section 73-1115 ("Construction managers; submission of proposals; ranking; negotiation of contract.") is part of the Revised Statutes of Nebraska, the codified statutory law of Nebraska. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Nebraska § 73-1115?
A common citation format is "Revised Statutes of Nebraska § 73-1115" (Nebraska). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Nebraska law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Nebraska official source linked on this page or consult a licensed Nebraska attorney.
How does Nebraska § 73-1115 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Nebraska can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification