§ 57-1619. Certificate of project completion; notice; hearing; consultation; issuance; conditions; effect.

(1) After carbon dioxide injections into a reservoir end and upon application by the storage operator, the commission shall consider issuing a certificate of project completion.

(2) The certificate may only be issued after public notice and hearing. The commission shall establish notice requirements for such hearing.

(3) The certificate may only be issued after the commission has consulted with the Department of Water, Energy, and Environment and the Underground Injection Control program permitting authority.

(4) The certificate may only be issued if the storage operator:

(a) Is in full compliance with all laws governing the storage facility;

(b) Shows that it has addressed all pending claims regarding the storage facility's operation;

(c) Shows that it has received an authorization of site closure from the applicable underground injection control program permitting authority for each storage facility injection well; and

(d) Shows that any wells, equipment, and facilities to be used in the post-closure period are in good condition and retain mechanical integrity.

(5) Once a certificate is issued:

(a) Title to the storage facility and to the stored carbon dioxide transfers, without payment of any compensation, to the State of Nebraska;

(b) Title acquired by the state includes all rights and interests in, and all responsibilities associated with, the stored carbon dioxide;

(c) The storage operator and all persons who generated any injected carbon dioxide streams are released from all regulatory requirements associated with the storage facility;

(d) Any financial assurance provided by the storage operator shall be released; and

(e) Monitoring and managing the storage facility is the state's responsibility to be overseen by the commission.

Source: official Nebraska text · Last verified 2026-08-27

Frequently Asked Questions About Nebraska § 57-1619

What does Revised Statutes of Nebraska § 57-1619 cover?

Section 57-1619 ("Certificate of project completion; notice; hearing; consultation; issuance; conditions; effect.") is part of the Revised Statutes of Nebraska, the codified statutory law of Nebraska. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Nebraska § 57-1619?

A common citation format is "Revised Statutes of Nebraska § 57-1619" (Nebraska). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Nebraska law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Nebraska official source linked on this page or consult a licensed Nebraska attorney.

How does Nebraska § 57-1619 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Nebraska can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Nebraska.