Full text of Michigan Michigan Compiled Laws § 18.1248 — Applicability of section; capital outlay project; carrying forward prior authorized projects; continuation or lapse of balance; termination of project; continuation of project beyond limits in section; conditions; carrying forward grant or grant-in-aid., with citation guidance and answers to common questions.
§ 18.1248. Applicability of section; capital outlay project; carrying forward prior authorized projects; continuation or lapse of balance; termination of project; continuation of project beyond limits in section; conditions; carrying forward grant or grant-in-aid.
(1) This section applies to all state agency, community college, and university capital outlay projects appropriated in any budget act. Projects authorized prior to the amendatory act that added this sentence shall be carried forward consistent with the provisions of this section in effect prior to the date of the amendatory act that added this sentence.
(2) Appropriations made in any budget act for a planning project shall not lapse to the fund from which appropriated at the end of the fiscal year, but shall continue until the purposes for which the sums were appropriated are completed. However, planning authorization for each project which has not been authorized for final design and construction in an appropriation act shall be terminated 24 months after the last day of the fiscal year in which the authorization was originally made, unless the project is specifically reauthorized in a budget act. The termination of authorization in the immediately preceding sentence does not apply if program and schematic planning documents are submitted by community colleges and universities within the time frame specified in the immediately preceding sentence.
(3) Appropriations made in any budget act for final design and construction shall not lapse to the fund from which they are appropriated at the end of the fiscal year, but shall continue until the purposes for which the sums were appropriated are completed. However, final design and construction authorization for each project where construction has not commenced shall be terminated 36 months after the last day of the fiscal year in which the authorization was originally made, unless the project is specifically reauthorized in a budget act.
(4) A capital outlay project may be continued beyond the limitations contained in this section if 1 or more of the following conditions apply:
(a) A bid for the start of construction of the project is awarded or construction of the project has commenced.
(b) A capital outlay project for the purchase of property in which a contract is entered into, but the acquisition is not completed. Only the amount necessary to complete the purchase of property pursuant to the contract shall be carried forward.
(c) A federal grant award is pending release.
(d) The project is subject to legal action, the balance shall lapse 30 days after the legal action is settled, or 30 days after a final order is entered, whichever is later.
(e) The unobligated balance of the appropriations for the project may continue for 12 months after a project is substantially completed.
(f) Not later than 45 days after the conclusion of the fiscal year, the director shall notify the JCOS and the fiscal agencies of planning and construction authorizations that will continue beyond limitations specified under this section.
(5) An unexpended balance which is to lapse pursuant to this section shall lapse to the fund from which the appropriation is made.
(6) A grant or grant-in-aid appropriated for the demolition, acquisition, construction, repair, or maintenance of capital assets shall not be reduced, adjusted, delayed, impounded, lapsed, or otherwise altered by the director for any purpose without legislative approval and shall be carried forward until the work is completed or for 36 months after the last day of the fiscal year in which the construction appropriation was originally made, whichever comes first.
Source: official Michigan text · Last verified 2026-08-27
Frequently Asked Questions About Michigan § 18.1248
What does Michigan Compiled Laws § 18.1248 cover?
Section 18.1248 ("Applicability of section; capital outlay project; carrying forward prior authorized projects; continuation or lapse of balance; termination of project; continuation of project beyond limits in section; conditions; carrying forward grant or grant-in-aid.") is part of the Michigan Compiled Laws, the codified statutory law of Michigan. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Michigan § 18.1248?
A common citation format is "Michigan Compiled Laws § 18.1248" (Michigan). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Michigan law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Michigan official source linked on this page or consult a licensed Michigan attorney.
How does Michigan § 18.1248 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Michigan can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Michigan.