Massachusetts § 39I - Deviations from plans and specifications
Full text of Massachusetts Massachusetts General Laws § 39I — Deviations from plans and specifications, with citation guidance and answers to common questions.
§ 39I. Deviations from plans and specifications
Section 39I. Every contractor having a contract for the construction, alteration, maintenance, repair or demolition of, or addition to, any public building or public works for the commonwealth, or of any political subdivision thereof, shall perform all the work required by such contract in conformity with the plans and specifications contained therein. No wilful and substantial deviation from said plans and specifications shall be made unless authorized in writing by the awarding authority or by the engineer or architect in charge of the work who is duly authorized by the awarding authority to approve such deviations. In order to avoid delays in the prosecution of the work required by such contract such deviation from the plans or specifications may be authorized by a written order of the awarding authority or such engineer or architect so authorized to approve such deviation. Within thirty days thereafter, such written order shall be confirmed by a certificate of the awarding authority stating: (1) If such deviation involves any substitution or elimination of materials, fixtures or equipment, the reasons why such materials, fixtures or equipment were included in the first instance and the reasons for substitution or elimination, and, if the deviation is of any other nature, the reasons for such deviation, giving justification therefor; (2) that the specified deviation does not materially injure the project as a whole; (3) that either the work substituted for the work specified is of the same cost and quality, or that an equitable adjustment has been agreed upon between the contracting agency and the contractor and the amount in dollars of said adjustment; and (4) that the deviation is in the best interest of the contracting authority.
Such certificate shall be signed under the penalties of perjury and shall be a permanent part of the file record of the work contracted for.
Whoever violates any provision of this section wilfully and with intent to defraud shall be punished by a fine of not more than five thousand dollars or by imprisonment for not more than six months, or both.
Frequently Asked Questions About Massachusetts § 39I
What does Massachusetts General Laws § 39I cover?
Section 39I ("Deviations from plans and specifications") is part of the Massachusetts General Laws, the codified statutory law of Massachusetts. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Massachusetts § 39I?
A common citation format is "Massachusetts General Laws § 39I" (Massachusetts). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Massachusetts law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Massachusetts official source linked on this page or consult a licensed Massachusetts attorney.
How does Massachusetts § 39I apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Massachusetts can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Massachusetts.