§ 23-303.

    A Program shall include:

        (1)    the major projects that the Commission determines may be required in each of the next 6 fiscal years:

            (i)    in the sanitary district; and

            (ii)    in geographical areas outside the sanitary district that the Commission determines are appropriate to include in the Program;

        (2)    a statement of the objectives and the relationship to the long–range development plans designated by each county for each major project;

        (3)    a projected construction schedule, an estimate of cost, and a statement of funding sources, including contributions that may be required for the construction of a major project;

        (4)    the information and documentation for each major project that the Commission is required to submit for the 6–year period covered by the Program under Title 9, Subtitle 5 of the Environment Article;

        (5)    the addition of a new major project and the deletion, modification, or rescheduling of a previously approved major project for which a construction contract has not been awarded or will not be awarded during the fiscal year in which the Program is being submitted;

        (6)    an indication, by major project, of the mains for which construction contributions have been made or committed and the amounts of contributions as of the date of the preparation of the Program;

        (7)    additional information for major projects for which contributions are made or committed before approval or amendment of the Program; and

        (8)    for each major project, as applicable:

            (i)    the estimated maximum diameter, length, and location of water and sewer mains;

            (ii)    the design capacity and approximate location of pumping stations;

            (iii)    the maximum population that could be served by each sewer construction item as the item is proposed to be designed;

            (iv)    the maximum area limits that could be served by gravity systems for each sewer system construction item and the area that each item is designed to serve, with the area limits set forth in a general narrative statement and on a map;

            (v)    the demonstrated need for each major project, including a presentation of appropriate facts justifying the proposed construction; and

            (vi)    the estimated cost of each construction item in the Program.

Frequently Asked Questions About Maryland § 23-303

What does Maryland Code § 23-303 cover?

Section 23-303 is part of the Maryland Code, the codified statutory law of Maryland. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Maryland § 23-303?

A common citation format is "Maryland Code § 23-303" (Maryland). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Maryland law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Maryland official source linked on this page or consult a licensed Maryland attorney.

How does Maryland § 23-303 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Maryland can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Maryland.