Louisiana § RS 39:105 - Capital Outlay reports to Joint Legislative Committee on Capital Outlay

Full text of Louisiana Louisiana Civil Code § RS 39:105 — Capital Outlay reports to Joint Legislative Committee on Capital Outlay, with citation guidance and answers to common questions.

§ RS 39:105. Capital Outlay reports to Joint Legislative Committee on Capital Outlay

            A.(1) The office of facility planning and control and any state agency authorized to administer capital outlay appropriations shall submit to the Joint Legislative Committee on Capital Outlay an annual written report no later than the first day of February. The report shall include the following information for each project included in the prior year's capital outlay budget:

            (a) The title of the project.

            (b) The total budget for the project from all means of financing.

            (c) A breakdown of the funding of the project including all cash and general obligation bond funding of the project.

            (d) The amount of state and local funds, including local match funds, expended on the project.

            (e) The amount of project funding that has been encumbered, including all cash and general obligation bond cash and noncash lines of credit approved for the project.

            (f) The total amount of funds the project will need to spend in the next fiscal year.

            (g) The current status of the project as either active or complete.

            (h) If the project is complete, the total amount of unspent appropriations remaining on the project, including the means of finance of the funds.

            (2) Each project which is funded through a cash means of finance or which received advance funding in a bond sale shall also be included in the annual report required in Paragraph (1) of this Subsection regardless of whether the project was in the prior year's capital outlay budget. Additionally, the office of facility planning and control shall continue to include each such project in the annual report until a certificate of completion for the project has been issued by the entity administering the project.

            B.(1) The office of facility planning and control and any state agency authorized to administer capital outlay appropriations shall submit to the Joint Legislative Committee on Capital Outlay, an annual written progress report no later than the first day of February, of the nonstate projects included in the current year's capital outlay budget which have been funded by the legislature, whether such funding was by appropriation or by bond authorization for which:

            (a) The cooperative endeavor agreement or any amendments thereto, with the state have not been fully executed. The project manager and the nonstate entity shall give a written explanation as to why the agreement has not been fully executed.

            (b) The nonstate projects which have a fully executed cooperative endeavor or amendment but which have not received the approval of the office of facility planning and control, of a proposed contract for the design or engineering of the project, including an explanation by the project manager and the nonstate entity as to the reason the contract has not been fully approved.

            (c) The nonstate projects which have a fully executed cooperative endeavor, have completed the design phase, and have not begun the construction phase of the project, including an explanation of the reasons that construction has not begun by the project manager and the nonstate entity.

            (2) A copy of each report shall be sent to each member of the legislature whose district includes one or more projects on the list.

            C. The office of facility planning and control shall submit the report in a format that can be edited.

            Acts 2016, No. 419, §1; Acts 2018, No. 653, §1, eff. June 1,2018; Acts 2023, No. 82, §1, eff. July 1, 2024.

Source: official Louisiana text · Last verified 2026-08-27

Frequently Asked Questions About Louisiana § RS 39:105

What does Louisiana Civil Code § RS 39:105 cover?

Section RS 39:105 ("Capital Outlay reports to Joint Legislative Committee on Capital Outlay") is part of the Louisiana Civil Code, the codified statutory law of Louisiana. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Louisiana § RS 39:105?

A common citation format is "Louisiana Civil Code § RS 39:105" (Louisiana). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Louisiana law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Louisiana official source linked on this page or consult a licensed Louisiana attorney.

How does Louisiana § RS 39:105 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Louisiana can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Louisiana.