Indiana § 8-1-39-9 - Petition for TDSIC; annual plan update; recovery and deferral of TDSIC costs and capital expenditures; timing; petition for review of basic rates and charges before plan expiration; exception

Full text of Indiana Indiana Code § 8-1-39-9 — Petition for TDSIC; annual plan update; recovery and deferral of TDSIC costs and capital expenditures; timing; petition for review of basic rates and charges before plan expiration; exception, with citation guidance and answers to common questions.

§ 8-1-39-9. Petition for TDSIC; annual plan update; recovery and deferral of TDSIC costs and capital expenditures; timing; petition for review of basic rates and charges before plan expiration; exception

Sec. 9. (a) Subject to subsection (d), a public utility that provides electric or gas utility service may file with the commission rate schedules establishing a TDSIC that will allow the periodic automatic adjustment of the public utility's basic rates and charges to provide for timely recovery of eighty percent (80%) of approved capital expenditures and TDSIC costs. The petition must:

(1) use the customer class revenue allocation factor based on firm load approved in the public utility's most recent retail base rate case order;

(2) include the public utility's TDSIC plan for eligible transmission, distribution, and storage system improvements; and

(3) identify projected effects of the plan described in subdivision (2) on retail rates and charges.

The public utility shall provide a copy of the petition to the office of the utility consumer counselor when the petition is filed with the commission.

(b) The public utility shall update the public utility's TDSIC plan under subsection (a)(2) at least annually. An update may include a petition for approval of:

(1) a targeted economic development project under section 11 of this chapter; or

(2) transmission, distribution, and storage system improvements not described in the public utility's TDSIC plan most recently approved by the commission under section 10 of this chapter.

(c) A public utility that recovers capital expenditures and TDSIC costs under subsection (a) shall defer the remaining twenty percent (20%) of approved capital expenditures and TDSIC costs, including depreciation, allowance for funds used during construction, and post in service carrying costs, and shall recover those capital expenditures and TDSIC costs as part of the next general rate case that the public utility files with the commission.

(d) Except as provided in section 15 of this chapter, a public utility may not file a petition under subsection (a) within nine (9) months after the date on which the commission issues an order changing the public utility's basic rates and charges with respect to the same type of utility service.

(e) This subsection does not apply to an electricity supplier (as defined in IC 8-1-46-6) that:

(1) is subject to a multi-year rate plan under IC 8-1-46; or

(2) petitions the commission for approval of a multi-year rate plan under IC 8-1-46;

during the term of the electricity supplier's approved TDSIC plan. A public utility that implements a TDSIC under this chapter shall, before the expiration of the public utility's approved TDSIC plan, petition the commission for review and approval of the public utility's basic rates and charges with respect to the same type of utility service.

(f) A public utility may file a petition under this section not more than one (1) time every six (6) months.

(g) Actual capital expenditures and TDSIC costs that exceed the approved capital expenditures and TDSIC costs require specific justification by the public utility and specific approval by the commission before being authorized for recovery in customer rates.

As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019, SEC.3; P.L.36-2026, SEC.9.

Source: official Indiana text · Last verified 2026-08-27

Frequently Asked Questions About Indiana § 8-1-39-9

What does Indiana Code § 8-1-39-9 cover?

Section 8-1-39-9 ("Petition for TDSIC; annual plan update; recovery and deferral of TDSIC costs and capital expenditures; timing; petition for review of basic rates and charges before plan expiration; exception") is part of the Indiana Code, the codified statutory law of Indiana. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Indiana § 8-1-39-9?

A common citation format is "Indiana Code § 8-1-39-9" (Indiana). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Indiana law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Indiana official source linked on this page or consult a licensed Indiana attorney.

How does Indiana § 8-1-39-9 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Indiana can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Indiana.