§ 36-9-27-80.5. Construction contract changes in specification; change orders
Sec. 80.5. (a) If a change in the original specifications of a contract for the construction or reconstruction of a drain becomes necessary during the construction or reconstruction, the county surveyor may issue a change order to add, delete, or change an item in the contract. A change order issued under this subsection becomes an addendum to the contract.
(b) The county surveyor may issue a change order under subsection (a) without obtaining prior approval from the board. The county surveyor shall report a change order issued under subsection (a) to the board at the next meeting of the board following the issuance of the change order.
(c) A change order issued under subsection (a) must be directly related to the drain project that is the subject of the original contract.
(d) The amount of a contract plus the amount of all change orders to the contract issued under this section may not exceed the following by more than twenty percent (20%):
(1) The construction costs estimated by the county surveyor under section 61(8) of this chapter.
(2) The reconstruction costs estimated by the county surveyor under section 49(c) of this chapter.
As added by P.L.154-1993, SEC.8.
Frequently Asked Questions About Indiana § 36-9-27-80.5
What does Indiana Code § 36-9-27-80.5 cover?
Section 36-9-27-80.5 ("Construction contract changes in specification; change orders") is part of the Indiana Code, the codified statutory law of Indiana. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Indiana § 36-9-27-80.5?
A common citation format is "Indiana Code § 36-9-27-80.5" (Indiana). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Indiana law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Indiana official source linked on this page or consult a licensed Indiana attorney.
How does Indiana § 36-9-27-80.5 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Indiana can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Indiana.