Indiana § 36-7-4-1324 - Ordinance; installment payment plan; fee upon permit issuance; interest; penalty for late payment

Full text of Indiana Indiana Code § 36-7-4-1324 — Ordinance; installment payment plan; fee upon permit issuance; interest; penalty for late payment, with citation guidance and answers to common questions.

§ 36-7-4-1324. Ordinance; installment payment plan; fee upon permit issuance; interest; penalty for late payment

Sec. 1324. (a) An impact fee ordinance must include an installment payment plan. The installment payment plan must at least offer a fee payer the option of paying part of an impact fee in equal installment payments if the impact fee is greater than five thousand dollars ($5,000). In an installment plan under this section:

(1) a maximum of five thousand dollars ($5,000) or five percent (5%) of the impact fee, whichever is greater, may become payable on the date the structural building permit is issued for the development on which the fee is imposed;

(2) the first installment may not become due and payable less than one (1) year after the date the structural building permit is issued for the development on which the fee is imposed; and

(3) the last installment may not be due and payable less than two (2) years after the date the structural building permit is issued for the development on which the fee is imposed.

(b) An impact fee ordinance may require an impact fee of five thousand dollars ($5,000) or less to be paid in full on the date the structural building permit is issued for the development on which the impact fee is imposed.

(c) An impact fee ordinance may provide that a reasonable rate of interest, not to exceed the prejudgment rate of interest in effect at the time the interest accrues, may be charged if the fee payer elects to pay in installments. If interest is charged, the ordinance must provide that interest accrues only on the portion of the impact fee that is outstanding and does not begin to accrue until the date the structural building permit is issued for the development or the part of the development on which the impact fee is imposed.

(d) An impact fee ordinance may provide that if all or part of an installment is not paid when due and payable, the amount of the installment shall be increased on the first day after the installment is due and payable by a penalty amount equal to ten percent (10%) of the installment amount that is overdue. If interest is charged under subsection (c), the interest shall be charged on the penalty amount.

As added by P.L.221-1991, SEC.25.

Source: official Indiana text · Last verified 2026-08-27

Frequently Asked Questions About Indiana § 36-7-4-1324

What does Indiana Code § 36-7-4-1324 cover?

Section 36-7-4-1324 ("Ordinance; installment payment plan; fee upon permit issuance; interest; penalty for late payment") is part of the Indiana Code, the codified statutory law of Indiana. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Indiana § 36-7-4-1324?

A common citation format is "Indiana Code § 36-7-4-1324" (Indiana). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Indiana law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Indiana official source linked on this page or consult a licensed Indiana attorney.

How does Indiana § 36-7-4-1324 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Indiana can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Indiana.