§ 13-18-27-16. Time limit for review authority's preliminary determination of whether construction plan is substantially complete

Sec. 16. (a) A review authority to which a construction plan is submitted must make a preliminary determination whether the construction plan is substantially complete before the end of:

(1) the tenth business day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site; or

(2) the fourteenth business day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site.

(b) If a review authority to which a construction plan is submitted under subsection (a):

(1) makes a preliminary determination that the construction plan is substantially complete; and

(2) notifies the project site owner of its favorable preliminary determination;

before the end of the tenth business day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth business day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, the project site owner may submit a notice of intent letter including the information required by the general permit and, forty-eight (48) hours after submission of the notice of intent letter, may begin the construction project, including the land disturbing activities of the construction project.

(c) If a review authority to which a construction plan for a small or very small construction activity site or a large construction activity site is submitted under subsection (a) does not notify the project site owner before the end of the tenth business day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth business day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, of its preliminary determination as to whether the construction plan is substantially complete, the project site owner may submit a notice of intent letter including the information required by the general permit and, forty-eight (48) hours after submission of the notice of intent letter, may begin the construction project, including the land disturbing activities of the construction project.

(d) If a review authority to which a construction plan is submitted under subsection (a) notifies the project site owner before the end of the tenth business day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth business day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, of its preliminary determination that the construction plan is not substantially complete, the project site owner may not submit a notice of intent letter until the review authority makes a conclusive favorable determination concerning the construction plan under the general permit or the applicable ordinance of the MS4 community.

(e) If a review authority to which a construction plan is submitted under subsection (a):

(1) makes a preliminary determination that the construction plan is substantially complete; and

(2) makes a conclusive unfavorable determination concerning the construction plan under the general permit or the applicable ordinance of the MS4 community;

the land disturbing activities of the construction project must stop when the review authority notifies the project site owner of the review authority's conclusive unfavorable determination concerning the construction plan.

As added by P.L.248-2019, SEC.14. Amended by P.L.135-2026, SEC.179.

Source: official Indiana text · Last verified 2026-08-27

Frequently Asked Questions About Indiana § 13-18-27-16

What does Indiana Code § 13-18-27-16 cover?

Section 13-18-27-16 ("Time limit for review authority's preliminary determination of whether construction plan is substantially complete") is part of the Indiana Code, the codified statutory law of Indiana. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Indiana § 13-18-27-16?

A common citation format is "Indiana Code § 13-18-27-16" (Indiana). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Indiana law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Indiana official source linked on this page or consult a licensed Indiana attorney.

How does Indiana § 13-18-27-16 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Indiana can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Indiana.