§ 5306. Contract Clauses and Their Administration.
(a) Contract Clauses. The Policy Office shall promulgate regulations requiring the inclusion in Guam
construction contracts of clauses providing for adjustments in prices, time of performance, or other contract
provisions, as appropriate, and covering the following subjects:
(1) the unilateral right of Guam to order in writing:
(A) changes in the work within the scope of the contract; and
(B) changes in the time of performance of the contract that do not alter the scope of the
contract;
(2) variations occurring between estimated quantities of work in a contract and actual quantities;
(3) suspension of work ordered by Guam; and
(4) site conditions differing from those indicated in the contract, or ordinarily encountered, except
that differing site conditions clauses promulgated by the Policy Office need not be included in a
contract:
(A) when the contract is negotiated;
COL 2026-04-23
(B) when the contractor provides the site or design; or
(C) when the parties have otherwise agreed with respect to the risk of differing site
conditions.
(b) Price Adjustments.
(1) Adjustments in price pursuant to clauses promulgated under Subsection (a) of this Section
shall be computed in one or more of the following ways:
(A) by agreement on a fixed price adjustment before commencement of the pertinent
performance or as soon thereafter as practicable;
(B) by unit prices specified in the contract or subsequently agreed upon;
(C) by the costs attributable to the events or situations under such clauses with adjustment
of profit or fee, all as specified in the contract or subsequently agreed upon;
(D) in such other manner as the contracting parties may mutually agree; or
(E) in the absence of agreement by the parties, by a unilateral determination by Guam of the
costs attributable to the events or situations under such clauses with adjustment of profit or fee,
all as computed by Guam in accordance with applicable sections of the regulations promulgated
under Chapter 7 and subject to the provisions of Chapter 9 of this Chapter.
(2) A contractor shall be required to submit cost or pricing data if any adjustment in contract price
is subject to the provisions of 5232 of this Chapter.
(c) Additional Contract Clauses. The Policy Office shall promulgate regulations requiring the
inclusion in Guam construction contracts of clauses providing for appropriate remedies and covering the
following subjects:
(1) liquidated damages as appropriate;
(2) specified excuses for delay or non-performance;
(3) termination of the contract for default; and
(4) termination of the contract in whole or in part for the convenience of Guam.
(d) Modification of Required Clauses. The Director of Public Works or the head of a purchasing
agency may vary the clauses promulgated by the Policy Office under Subsection (a) and Subsection (c) of
this Section for inclusion in any particular Guam construction contract, provided, that any variations are
supported by a written determination that states the circumstances justifying such variations, and provided,
that notice of any such material variation be stated in the invitation for bids or request for proposals.
Frequently Asked Questions About Guam § 5306
What does Guam Code Annotated § 5306 cover?
Section 5306 ("Contract Clauses and Their Administration.") is part of the Guam Code Annotated, the codified statutory law of Guam. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Guam § 5306?
A common citation format is "Guam Code Annotated § 5306" (Guam). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Guam law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Guam official source linked on this page or consult a licensed Guam attorney.
How does Guam § 5306 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Guam can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Guam.