§ 16-32l. l . Residential customer credits for distribution-system service outage. Recovery of costs. Waiver of requirements.
Sec. 16-32l. Residential customer credits for distribution-system service outage. Recovery of costs. Waiver of requirements. (a) For the purposes of this section:
(1) “Emergency” means any hurricane, tornado, storm, flood, high water, wind-driven water, tidal wave, earthquake, landslide, mudslide, snowstorm, drought or fire explosion that results in sixty-nine per cent or less of the electric distribution company's customers experiencing an outage at the period of peak electrical demand;
(2) “Electric distribution company” has the same meaning as provided in section 16-1; and
(3) “After the occurrence of an emergency” means the conclusion of the emergency, as determined by the authority in its discretion, through a review of the following: (A) The time when the electric distribution company could first deploy resources safely in its service territory; (B) the first of any official declarations concerning the end of the emergency; or (C) the expiration of the first of any National Weather Service warning applicable to the service territory.
(b) Notwithstanding any other provision of the general statutes, on and after July 1, 2021, each electric distribution company shall provide to residential customers of such company a credit of twenty-five dollars, on the balance of such customer's account, for each day of distribution-system service outage that occurs for such customers for more than ninety-six consecutive hours after the occurrence of an emergency.
(c) Any costs incurred by an electric distribution company pursuant to this section shall not be recoverable.
(d) Not later than fourteen calendar days after the occurrence of an emergency, an electric distribution company may petition the authority for a waiver of the requirements of this section. Any petition for a waiver made under this subsection shall include the severity of the emergency, line and restoration crew safety issues and conditions on the ground, and shall be conducted as a contested case proceeding. The burden of proving that such waiver is reasonable and warranted shall be on the electric distribution company. In determining whether to grant such waiver, the authority shall consider whether the electric distribution company received approval and reasonable funding allowances, as determined by the authority, to meet infrastructure resiliency efforts to improve such company's performance.
(e) On or before January 1, 2021, the Public Utilities Regulatory Authority shall initiate a proceeding to consider the implementation of the residential customer credit and waiver provisions of this section and establish circumstances, standards and methodologies applicable to each electric distribution company and necessary to implement the provisions of this section, including any modifications to the ninety-six-consecutive-hour standard in subsection (b) of this section. The authority shall issue a final decision in such proceeding on or before July 1, 2021.
(Sept. Sp. Sess. P.A. 20-5, S. 10; P.A. 23-102, S. 17, 18.)
History: Sept. Sp. Sess. P.A. 20-5 effective October 2, 2020; P.A. 23-102 amended Subsec. (a) by redefining “emergency” in Subdiv. (1), designating definition of “electric distribution company” as Subdiv. (2), and adding Subdiv. (3) defining “after the occurrence of an emergency”, and amended Subsec. (d) by replacing “employee” with “line and restoration crew”.
Source: official Connecticut text · Last verified 2026-08-27
Frequently Asked Questions About Connecticut § 16-32l
What does Connecticut General Statutes § 16-32l cover?
Section 16-32l ("l . Residential customer credits for distribution-system service outage. Recovery of costs. Waiver of requirements.") is part of the Connecticut General Statutes, the codified statutory law of Connecticut. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Connecticut § 16-32l?
A common citation format is "Connecticut General Statutes § 16-32l" (Connecticut). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Connecticut law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Connecticut official source linked on this page or consult a licensed Connecticut attorney.
How does Connecticut § 16-32l apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Connecticut can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Connecticut.