Colorado § 40-7-113.5 - Civil penalties applicable to public utilities - exclusion from rate base.
Full text of Colorado Colorado Revised Statutes § 40-7-113.5 — Civil penalties applicable to public utilities - exclusion from rate base., with citation guidance and answers to common questions.
§ 40-7-113.5. Civil penalties applicable to public utilities - exclusion from rate base.
(1) (a) In addition to any other penalty otherwise authorized by law and except as otherwise provided in subsections (3), (4), and (5) of this section, a public utility furnishing electric, gas, water, water and sewer, or telecommunications service that intentionally violates any provision of articles 1 to 7 or 15 of this title 40 or of any rule, tariff, or order of the commission adopted or issued pursuant to articles 1 to 7 or 15 of this title 40, which provision is applicable to such utility, may be assessed a civil penalty of not more than seven thousand five hundred dollars; except that nothing in this subsection (1) shall be construed to authorize the imposition of civil penalties upon:
(I) A cooperative electric association that has voted to exempt itself from regulation pursuant to section 40-9.5-103;
(II) A cooperative telephone association;
(III) A municipally owned utility; or
(IV) A nonprofit generation and transmission electric corporation or association.
(b) Civil penalties assessed pursuant to this section shall be paid and credited to the general fund, in addition to any other sanctions that may be imposed pursuant to law; except that civil penalties assessed against an electric or gas utility shall be paid to the public utilities commission fixed utility fund created in section 40-2-114 (1)(b)(II) and shall be used for affordability programs or outreach and engagement directly related to income-qualified customers or disproportionately impacted communities. The amount of any such penalties paid shall not be an allowable expense for rate-making purposes.
(2) (a) The commission shall adopt rules specifying the amount of the civil penalties to be assessed for each violation pursuant to subsection (1) of this section. In determining the amount of civil penalties to be assessed for each violation, the commission shall consider factors including the utility size, the actual or potential harm of a violation, and any mitigating circumstances or actions of the utility.
(b) No public utility shall be assessed a civil penalty if the utility is already subject to an existing reparation due to a commission order, commission rule, or statutory provision for the same violation.
(3) If any public utility receives a second civil penalty assessment for a violation of the same statute, rule, or order within one year after the first violation, the civil penalty assessed for the second violation shall be no greater than twice the amount specified by rule for such violation.
(4) If any public utility receives more than two civil penalty assessments for violation of the same statute, rule, or order within one year, the civil penalty assessed for each such subsequent violation shall be no greater than three times the amount specified by rule for such violation.
(5) Notwithstanding any provision of this section to the contrary, the total amount of civil penalties assessed against one public utility under this section shall not exceed the lesser of the following:
(a) One hundred fifty thousand dollars in any six-month period; or
(b) In any twelve-month period, one percent of the utility's gross annual revenues from services regulated by the commission, based on the most recent fiscal year for which final revenue figures are available.
Source: L. 2008: Entire section added, p. 1798, § 20, effective July 1. L. 2026: IP(1)(a), (1)(b), and (2)(a) amended, (HB 26-1326), ch. 210, p. 1220, § 14, effective August 12.
Editor's note: Section 50(2) of chapter 210 (HB 26-1326), Session Laws of Colorado 2026, provides that the act changing this section applies to conduct occurring on or after August 12, 2026.
Source: official Colorado text · Last verified 2026-08-27
Frequently Asked Questions About Colorado § 40-7-113.5
What does Colorado Revised Statutes § 40-7-113.5 cover?
Section 40-7-113.5 ("Civil penalties applicable to public utilities - exclusion from rate base.") is part of the Colorado Revised Statutes, the codified statutory law of Colorado. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Colorado § 40-7-113.5?
A common citation format is "Colorado Revised Statutes § 40-7-113.5" (Colorado). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Colorado law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Colorado official source linked on this page or consult a licensed Colorado attorney.
How does Colorado § 40-7-113.5 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Colorado can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Colorado.