§ 40-2-132. Distribution system planning - definition - rules.
(1) The commission shall promulgate rules establishing the filing of a distribution system plan. The commission's rules must:
(a) Define the following terms:
(I) Distributed energy resources that include:
(A) Distributed renewable electric generation;
(B) Energy storage systems connected to the distribution grid;
(C) Microgrids;
(D) Energy efficiency measures; and
(E) Demand response measures; and
(II) Non-wires alternatives;
(b) Develop a methodology for evaluating the costs and net benefits of using distributed energy resources as non-wires alternatives;
(c) Determine a threshold for the size of a new distribution project, whether in dollars, meters, or another factor, as determined by the commission, for when a qualifying retail utility must consider implementation or use of non-wires alternatives, potentially including energy efficiency measures under utility programs for new electric service to any planned new neighborhoods or housing developments;
(d) Direct each qualifying retail utility to file a distribution system plan;
(e) Determine what shall be included in a distribution system plan, which at a minimum must include the following:
(I) Information regarding:
(A) System and substation historical data;
(B) Peak demand;
(C) Adoption of distributed energy resources; and
(D) Distribution system investments;
(II) To provide new electric service to any planned new neighborhoods or housing developments expected to include more than ten thousand new residences, a description of the qualifying retail utility's consideration of non-wires alternatives, potentially including energy efficiency measures under utility programs;
(III) An updated load forecast that includes any new load resulting from projected or forecasted growth from beneficial electrification programs;
(IV) A forecast of the growth of distributed energy resources for the years covered by the plan;
(V) A high-level summary of its planning process for addressing cyber and physical security risks. As part of the summary, the qualifying retail utility need not report any confidential, proprietary, or other information in the plan that could in any way compromise or decrease the qualifying retail utility's ability to prevent, mitigate, or recover from potential system disruptions caused by weather events, physical events, or cyber attacks.
(VI) A proposed cost-recovery method or mechanism for any non-wires alternative investments found to be outside the ordinary course of business;
(VII) A description of the qualifying retail utility's anticipated new distribution system expansion investments for the years covered by the plan;
(VIII) A process to evaluate the plan's feasibility and the economic impacts of using non-wires alternatives for certain projects;
(IX) An estimate of the year in which peak demand growth or distributed energy resource growth would merit analysis of new non-wires alternative projects; and
(X) Any other information that the commission deems relevant.
(2) The commission shall approve a qualifying retail utility's investment in non-wires alternatives if the commission finds the investment to be in the public interest.
(3) (a) The commission shall determine whether a qualifying retail utility's ratepayers would realize benefits from a non-wires alternative investment and whether the associated costs are just and reasonable.
(b) To evaluate the success of any non-wires alternative investment authorized pursuant to a qualifying retail utility's distribution system plan, the commission may adopt criteria, benchmarks, or accountability mechanisms with which the qualifying retail utility must comply.
(4) As used in this section, "qualifying retail utility" has the meaning described in section 40-2-124 (1); except that the term does not mean a municipally owned utility or a cooperative electric association.
Source: L. 2019: Entire section added, (SB 19-236), ch. 359, p. 3301, § 8, effective May 30.
Frequently Asked Questions About Colorado § 40-2-132
What does Colorado Revised Statutes § 40-2-132 cover?
Section 40-2-132 ("Distribution system planning - definition - rules.") is part of the Colorado Revised Statutes, the codified statutory law of Colorado. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Colorado § 40-2-132?
A common citation format is "Colorado Revised Statutes § 40-2-132" (Colorado). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Colorado law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Colorado official source linked on this page or consult a licensed Colorado attorney.
How does Colorado § 40-2-132 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Colorado can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Colorado.