§ 40-9.5-118. Net metering - rules.
(1) Definitions. As used in this section, unless the context otherwise requires:
(a) "Customer-generator" means an end-use electricity customer that generates electricity on the customer's side of the meter using eligible energy resources.
(b) "Eligible energy resources" has the meaning established in section 40-2-124.
(2) Each cooperative electric association shall allow a customer-generator's retail electricity consumption to be offset by the electricity generated from eligible energy resources on the customer-generator's side of the meter that are interconnected with the facilities of the cooperative electric association, subject to the following:
(a) Monthly excess generation. If a customer-generator generates electricity in excess of the customer-generator's monthly consumption, all such excess energy, expressed in kilowatt-hours, shall be carried forward from month to month and credited at a ratio of one to one against the customer-generator's energy consumption, expressed in kilowatt-hours, in subsequent months.
(b) Annual excess generation. Within sixty days after the end of each annual period, or within sixty days after the customer-generator terminates its retail service, the cooperative electric association shall account for any excess energy generation, expressed in kilowatt-hours, accrued by the customer-generator and shall credit such excess generation to the customer-generator in a manner deemed appropriate by the cooperative electric association.
(c) Nondiscriminatory rates. A cooperative electric association shall provide net metering service at nondiscriminatory rates.
(d) Interconnection standards. A cooperative electric association and a customer-generator shall comply with the interconnection standards and insurance requirements established in the rules adopted by the public utilities commission pursuant to section 40-2-124; except that the cooperative electric association may reduce or waive any of the insurance requirements; and except that the public utilities commission shall initiate a rule-making proceeding no later than October 1, 2008, for the purpose of addressing cooperative electric association system issues in its small generator interconnection procedures. A cooperative electric association shall not prevent or unreasonably burden the installation of a net metering system if such system includes protective equipment that prevents any export of customer-generated electricity from the customer's side of the meter. A cooperative electric association and a customer-generator shall comply with the rules adopted by the public utilities commission pursuant to section 40-2-124 (1.3) regarding meter collar adapters and with other commission rules regarding production meters.
(e) (I) Size specifications. Each cooperative electric association shall allow:
(A) Residential customer-generators to generate electricity subject to net metering up to ten kilowatts; and
(B) Commercial or industrial customer-generators to generate electricity subject to net metering up to twenty-five kilowatts.
(II) Each cooperative electric association may allow customer-generators to generate electricity subject to net metering in amounts in excess of the minimum amounts specified in subparagraph (I) of this paragraph (e). If the cooperative electric association denies interconnection to a customer-generator that has requested interconnection of a system with a capacity of twenty-five kilowatts or larger, the association shall provide a written technical or economic explanation of such denial to the customer.
(3) The cooperative electric association and the customer-generator shall indemnify, defend, and save the other party harmless from any and all damages, losses, or claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the other party's action or failure to act in relation to any obligations under this section, except in cases of gross negligence or intentional wrongdoing by the indemnified party.
Source: L. 2008: Entire section added, p. 188, § 2, effective August 5. L. 2026: (2)(d) amended, (HB 26-1007), ch. 127, p. 555, § 4, effective August 12.
Cross references: For the legislative declaration in HB 26-1007, see section 1 of chapter 127, Session Laws of Colorado 2026.
PART 2
SERVICE TERRITORIES WITHIN MUNICIPALITIES OWNING AND OPERATING ELECTRIC UTILITIES
Frequently Asked Questions About Colorado § 40-9.5-118
What does Colorado Revised Statutes § 40-9.5-118 cover?
Section 40-9.5-118 ("Net metering - rules.") is part of the Colorado Revised Statutes, the codified statutory law of Colorado. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.
How do I cite Colorado § 40-9.5-118?
A common citation format is "Colorado Revised Statutes § 40-9.5-118" (Colorado). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.
Is this the official text of Colorado law?
No. This page is for research and education and may not include the most recent amendments. For official current law, check the Colorado official source linked on this page or consult a licensed Colorado attorney.
How does Colorado § 40-9.5-118 apply to my situation?
Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Colorado can advise on how this section applies to you. Contact your state or local bar association for a referral.
Sources & Verification
Not legal advice. Verify against the official source and consult a licensed attorney in Colorado.