California § 8612 - In order to enforce a claim against a payment bond under this title, a claimant s

Full text of California Public Contract Code - PCC § 8612 — In order to enforce a claim against a payment bond under this title, a claimant s, with citation guidance and answers to common questions.

§ 8612. In order to enforce a claim against a payment bond under this title, a claimant s

(a) In order to enforce a claim against a payment bond under this title, a claimant shall give the preliminary notice provided in Chapter 2 (commencing with Section 8200). (b) If preliminary notice was not given as provided in Chapter 2 (commencing with Section 8200), a claimant may enforce a claim by giving written notice to the surety and the bond principal within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement. (c) Commencing July 1, 2012, and except as provided in subdivision (b), if the preliminary notice was required to be given by a person who has no direct contractual relationship with the contractor, and who has not given notice as provided in Chapter 2 (commencing with Section 8200), that person may enforce a claim by giving written notice to the surety and the bond principal, as provided in Section 8614, within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement. (d) Subdivision (c) shall not apply in either of the following circumstances: (1) All progress payments, except for those disputed in good faith, have been made to a subcontractor who has a direct contractual relationship with the general contractor to whom the claimant has provided materials or services. (2) The subcontractor who has a direct contractual relationship with the general contractor to whom the claimant has provided materials or services has been terminated from the project pursuant to the contract, and all progress payments, except those disputed in good faith, have been made as of the termination date. (e) Pursuant to Section 8200, this section shall not apply to a laborer, as defined under Section 8024. (f) This section shall become operative on July 1, 2012.

Source: official California text · Last verified 2026-08-27

Frequently Asked Questions About California § 8612

What does Public Contract Code - PCC § 8612 cover?

Section 8612 ("In order to enforce a claim against a payment bond under this title, a claimant s") is part of the Public Contract Code - PCC, the codified statutory law of California. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite California § 8612?

A common citation format is "Public Contract Code - PCC § 8612" (California). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of California law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the California official source linked on this page or consult a licensed California attorney.

How does California § 8612 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in California can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in California.