California § 71685 - Not later than the second Tuesday in February each year the board shall order an

Full text of California Public Contract Code - PCC § 71685 — Not later than the second Tuesday in February each year the board shall order an, with citation guidance and answers to common questions.

§ 71685. Not later than the second Tuesday in February each year the board shall order an

Not later than the second Tuesday in February each year the board shall order an engineering survey and report to be made regarding the ground water supplies of the district. The same shall include, among all other information and data which the board may require, the following: (a) Records, data and other information for the consideration of the board in its determination of the annual overdraft. (b) Records, data and other information for the consideration of the board in its determination of the accumulated overdraft as of the last day of the preceding water year. (c) A report, with supporting data, as to the total production of ground water from the ground water supplies within the district during the preceding water year. (d) A report, with supporting data, as to the changes during the preceding water year in the ground water levels and pressure levels or piezometric heights of the ground water contained within pressure-level areas of the district, and as to the effects thereof upon the ground water supplies within the district. (e) An estimate of the annual overdraft for the current water year and for the ensuing water year. (f) An estimate of the accumulated overdraft as of the last day of the current water year. (g) An estimate of the total production of ground water from the ground water supplies within the district for the current water year and for the ensuing water year. (h) An estimate of the changes during the current water year in the ground water levels, pressure levels or piezometric heights of the ground water contained within pressure-level areas of the district, and of the effects thereof upon the ground water supplies and makeup water requirements of the district. (i) An estimate of the quantity, source, and cost of water available for replenishment of the ground water supplies and meeting the makeup water requirements of the district during the ensuing water year under the provisions of Section 71687. (j) Records, data, estimates and other information for the consideration of the board in its determination of the makeup water requirements for the preceding, current and ensuing water years.

Source: official California text · Last verified 2026-08-27

Frequently Asked Questions About California § 71685

What does Public Contract Code - PCC § 71685 cover?

Section 71685 ("Not later than the second Tuesday in February each year the board shall order an") is part of the Public Contract Code - PCC, the codified statutory law of California. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite California § 71685?

A common citation format is "Public Contract Code - PCC § 71685" (California). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of California law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the California official source linked on this page or consult a licensed California attorney.

How does California § 71685 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in California can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in California.