California § 7159.6 - An extra work or change order is not enforceable against a buyer unless the chang

Full text of California Public Contract Code - PCC § 7159.6 — An extra work or change order is not enforceable against a buyer unless the chang, with citation guidance and answers to common questions.

§ 7159.6. An extra work or change order is not enforceable against a buyer unless the chang

(a) An extra work or change order is not enforceable against a buyer unless the change order sets forth all of the following: (1) The scope of work encompassed by the order. (2) The amount to be added or subtracted from the contract. (3) The effect the order will make in the progress payments or the completion date. (b) The buyer may not require a contractor to perform extra or change-order work without providing written authorization. (c) Failure to comply with the requirements of this section does not preclude the recovery of compensation for work performed based upon legal or equitable remedies designed to prevent unjust enrichment. (d) This section shall become operative on January 1, 2006.

Source: official California text · Last verified 2026-08-27

Frequently Asked Questions About California § 7159.6

What does Public Contract Code - PCC § 7159.6 cover?

Section 7159.6 ("An extra work or change order is not enforceable against a buyer unless the chang") is part of the Public Contract Code - PCC, the codified statutory law of California. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite California § 7159.6?

A common citation format is "Public Contract Code - PCC § 7159.6" (California). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of California law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the California official source linked on this page or consult a licensed California attorney.

How does California § 7159.6 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in California can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in California.