Arizona § 41-2617 - Contracts for procurement of construction; delay; recovery of damages by contractor

Full text of Arizona Arizona Revised Statutes § 41-2617 — Contracts for procurement of construction; delay; recovery of damages by contractor, with citation guidance and answers to common questions.

§ 41-2617. Contracts for procurement of construction; delay; recovery of damages by contractor

A contract for the procurement of construction shall include a provision which provides for negotiations between the state governmental unit and the contractor for the recovery of damages related to expenses incurred by the contractor for a delay for which the state governmental unit is responsible, which is unreasonable under the circumstances and which was not within the contemplation of the parties to the contract.  This section shall not be construed to void any provision in the contract which requires notice of delays, provides for arbitration or other procedure for settlement or provides for liquidated damages.

Source: official Arizona text · Last verified 2026-08-27

Frequently Asked Questions About Arizona § 41-2617

What does Arizona Revised Statutes § 41-2617 cover?

Section 41-2617 ("Contracts for procurement of construction; delay; recovery of damages by contractor") is part of the Arizona Revised Statutes, the codified statutory law of Arizona. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Arizona § 41-2617?

A common citation format is "Arizona Revised Statutes § 41-2617" (Arizona). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Arizona law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Arizona official source linked on this page or consult a licensed Arizona attorney.

How does Arizona § 41-2617 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Arizona can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification

Not legal advice. Verify against the official source and consult a licensed attorney in Arizona.