§ 12-552. Actions involving development of real property design, engineering and construction of improvements

A. Notwithstanding any other statute, an action or arbitration based in contract may not be instituted or maintained against a person who develops or develops and sells real property, or performs or furnishes the design, specifications, surveying, planning, supervision, testing, construction or observation of construction of an improvement to real property more than eight years after substantial completion of the improvement to real property.

B. Notwithstanding any other statute, a municipality or a county may not institute or maintain an action or arbitration against a person who develops or develops and sells real property or performs or furnishes the design, specifications, surveying, planning, supervision, testing, construction or observation of construction of an improvement to real property that is dedicated to the municipality or county more than eight years after the improvement to real property has been accepted by the municipality or county for ownership, operation and maintenance if the action or arbitration is based on either:

1. A municipal or county code, ordinance or other legal requirement.

2. A permit that is required as a condition of development.

C. The limitations of subsection B of this section do not apply to an action or arbitration that is based on a claim of a wilful, reckless or concealed violation of a municipal or county requirement.

D. Subsection B of this section does not limit any immunity or defense that is available to a municipality or county pursuant to chapter 7, article 2 of this title.

E. Notwithstanding subsection A or B of this section, in the case of injury to real property or an improvement to real property, if the injury occurred during the eighth year after the substantial completion or, in the case of a latent defect, was not discovered until the eighth year after substantial completion, an action to recover damages for injury to the real property may be brought within one year after the date on which the injury to real property or an improvement to real property occurred or a latent defect was discovered, but an action may not be brought more than nine years after the substantial completion of the improvement.

F. The limitations in subsections A, B and E of this section include any action based on implied warranty arising out of the contract or the construction, including implied warranties of habitability, fitness or workmanship.

G. This section does not apply to actions for personal injury or death or shorten the period of warranty provided in an express written warranty.

H. For the purposes of subsections A, E and F of this section, an improvement to real property is considered substantially complete when any of the following first occurs:

1. It is first used by the owner or occupant of the improvement.

2. It is first available for use after having been completed according to the contract or agreement covering the improvement, including agreed changes to the contract or agreement.

3. Final inspection, if required, by the governmental body that issued the building permit for the improvement.

I. In this section an action based in contract is an action based on a written real estate contract, sales agreement, construction agreement, conveyance or written agreement for construction or for the services set forth in subsection A of this section. This section does not extend the period prescribed by the laws of this state for bringing any action. If a shorter period of limitation is prescribed for a specific action, the shorter period governs.

J. With respect to an improvement to real property that was substantially complete on or before September 15, 1989, the eight and nine-year periods established in subsections A and E of this section shall begin to run on September 15, 1989. Notwithstanding the provisions of subsection H of this section and section 12-505, subsection A, this subsection applies to claims that accrued before May 14, 1992.

Source: official Arizona text · Last verified 2026-08-27

Frequently Asked Questions About Arizona § 12-552

What does Arizona Revised Statutes § 12-552 cover?

Section 12-552 ("Actions involving development of real property design, engineering and construction of improvements") is part of the Arizona Revised Statutes, the codified statutory law of Arizona. It sets out the legal rule or procedure described in the text above. Statutes are amended regularly, so always verify against the official source.

How do I cite Arizona § 12-552?

A common citation format is "Arizona Revised Statutes § 12-552" (Arizona). Legal writing may require the code abbreviation, section number, and year or edition. Match the style required by your court, professor, or publisher.

Is this the official text of Arizona law?

No. This page is for research and education and may not include the most recent amendments. For official current law, check the Arizona official source linked on this page or consult a licensed Arizona attorney.

How does Arizona § 12-552 apply to my situation?

Statutes are interpreted in context, and application depends on your specific facts. Only a licensed attorney in Arizona can advise on how this section applies to you. Contact your state or local bar association for a referral.

Sources & Verification